D.C. Cir. No. 23-1133
Order affirming ALJ initial decision, that SPP proposal to place Nixa transmission facilities in Zone 10 is consistent with cost causation principles and is otherwise just and reasonable. Southwest Power Pool, Inc., 182 FERC ¶ 61,141 (2023), order on reh’g, 184 FERC ¶ 61,004 (2023).

This page was last updated on December 27, 2023