Introduction
On January 30, 2026, Federal Energy Regulatory Commission (FERC or the Commission) issued a Notice of Availability requesting public comments on the draft Environmental Impact Statement (EIS) for the Mississippi Crossing Project proposed by Tennessee Gas Pipeline Company, LLC and South System Expansion 4 Project proposed by Southern Natural Gas Company, LLC (Docket Nos. CP25-514-000 and CP25-517-000). Any person wishing to comment on the draft EIS may do so.
On December 31, 2025, the FERC issued a Notice of Schedule for the Mississippi Crossing and South System Expansion 4 Projects. These projects are covered under Title 41 of the Fixing America’s Surface Transportation Act (FAST-41). Under FAST-41 agencies are to publish completion dates for all federal environmental reviews and authorizations. This notice identifies the Commission's anticipated schedule for issuance of the final orders for the projects, which is based on the anticipated issuance date for the final environmental impact statement (EIS).
The Commission’s anticipated issuance of the Final EIS is June 26, 2026.
The Commission’s anticipated issuance of the Final Order is no later than July 31, 2026.
If a schedule change becomes necessary, additional notice will be provided so that interested parties and the relevant agencies are kept informed of the projects' progress.
More information can be found in FERC Docket No. CP25-514-000 and CP25-517-000 in FERC’s eLibrary. Please note that the project has not been approved at this time.
Project Route and Facilities
The planned pipeline project is planned to transport natural gas from Greenville, Mississippi to Butler, Alabama. Tennessee Gas plans to construct approximately 206 miles of new natural gas pipeline, (3) three compressor stations, (4) four meter stations, and (3) three overpressure protection facilities. The facilities would provide up to 1.5 billion cubic feet per day of new natural gas transportation capacity.
On June 30, 2025, Tennessee Gas submitted several maps on the Project to the docket. To view and download these maps, please visit FERC's eLibrary and search Docket No. CP25-514-000.
Public Participation Opportunities
Schedule for Environmental Review
| January 2026 | A draft of the Environmental Impact Statement was issued. |
| June 2026 | The Issuance of Notice of Availability of the final EIS is scheduled. |
| September 2026 |
The Federal Authorization Decision Deadline is scheduled. |
There are three methods you can use to submit your comments to FERC.
1. eComment
You can file your comments electronically using the eComment feature in FERC Online. Using eComment is an easy method for submitting brief, text-only comments.
2. eFiling
You can file your comments electronically by using the eFiling feature in FERC Online. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making. A comment on a particular project is considered a “Comment on a Filing.”
3. File a paper copy
You can file a paper copy of your comments by mailing them to FERC. Be sure to reference the Project Docket No. CP25-517-000 for South System Expansion 4 Project and CP25-514-000 for Mississippi Crossing Project on your letter Submissions sent via the U.S. Postal Service must be addressed to:
Debbie-Anne A. Reese, Secretary
Federal Energy Regulatory Commission
888 First Street NE, Room 1A
Washington, DC 20426
Submissions sent via any other carrier must be addressed to:
Debbie-Anne A. Reese, Secretary
Federal Energy Regulatory Commission
12225 Wilkins Avenue
Rockville, Maryland 20852
More Information and Staying Updated
You may learn more about the Project through FERC's eLibrary. When searching for the Mississippi Crossing Project, please enter Docket No. CP25-514-000 in the “Enter Docket Number” text box. When searching for South System Expansion 4 Project, please enter Docket No. CP25-517-000 in the “Enter Docket Number” text box. FERC’s Office of Public Participation provides an educational video and demonstration on using eLibrary: WorkshOPP and Demonstration: FERC’s eLibrary.
Stay Informed
Follow OPP on its social media channels:
OPP regularly sends announcements about upcoming participation opportunities and meetings with interested stakeholders and organizations via its social media channels.
You may also sign up for FERC’s eSubscription service. eSubscription notifies you via email about submittals and issuances on the project. Please visit www.ferc.gov/esubscription.
You are also encouraged to contact OPP staff to learn more about the Project and participation at FERC by email at [email protected] or phone at 202-502-6595. All media inquiries should be directed to [email protected].
Resources
Guides on Public Participation
Educational Videos
- Learn to eFile, eComment, and eSubscribe
- How to File an Intervention Using FERC’s Online System
- Filing Comments Workshop and Demonstration
- Submitting Powerful Comments Workshop
Tips on Public Participation
Informational Handouts
- About FERC
- Natural Gas Pre-filing Open Houses: Public Participation and What to Expect
- Natural Gas Scoping Sessions: Public Participation and What to Expect
Background
- November 8, 2024: Tennessee Gas Pipeline Company, L.L.C files a request to initiate the Pre-filing Process with FERC
- December 6, 2024: FERC approves Tennessee Gas Pipeline Company to begin the Pre-filing Review for Mississippi Crossing Project
- December 18, 2024: Draft Resource Report 1 and 10 are submitted which include maps, Open House schedule, and Summary of Alternatives
- March 3, 2025: FERC issues a Notice of Scoping Period
- March 4, 2025: FERC issues an ERRATA Notice correcting the March 31, 2025, comment deadline to April 7, 2025.
- January 27 - March 5, 2025: Open Houses were hosted by Southern Natural Gas during the Pre-filing Process. Members of the public had several opportunities to express their views, concerns, and issues with the project.
-
March - April 2025: Public Scoping session occurred in Mississippi, Alabama, and Georgia.
- July 12, 2025: FERC Establishes a Notice of Application and Established Intervention Deadline.
- August 4, 2025: FERC issues an order granting waiver.
-
September 5, 2025: FERC Issues Notice of Intent to Prepare an Environmental Impact Statement.
-
December 31, 2025: FERC issues Notice of Schedule for the Final Order for the Mississippi Crossing Project and the South System Expansion 4.
-
January 30, 2026: FERC issues Draft Environmental Impact Statement for Tennessee Gas Pipeline Company, LLC et al. re the Mississippi Crossing Project and the South System Expansion 4 Project.
-
February 10, 2026: FERC Issues Errata Notice – Meeting location change
-
February 25, 2026: FERC Issues Errata Notice – Address correction for DEIS meeting
-
March 23, 2026: Comments on the Draft EIS were due.
Office of Public Participation's Outreach Corner
The Office of Public Participation (OPP) is authorized to support public participation in FERC proceedings pursuant to Section 319 of the Federal Power Act. OPP coordinates with and provides assistance to members of the public as to participation in, and understanding of, FERC proceedings. OPP provides outreach to community groups, community members, landowners and other interested parties potentially impacted by infrastructure projects.
OPP’s outreach conducted for the Mississippi Crossing Project in Docket Nos. CP25-514-000, CP25-514-001, PF25-2; and South System Expansion 4 Pipeline Project in Docket Nos. CP25-517-000, CP25-517-001, PF25-1, included:
-
On January 17, 2025, affected landowners and concerned citizens were notified via the U.S. Postal Service that FERC is seeking public comments on Mississippi Crossing and the South System Expansion 4 Pipeline Projects located in Mississippi, Alabama, and George. FERC educational brochures and letters were mailed to inform landowners and citizens of the project comment deadline.
-
Coordinated social media campaigns in the first quarter of 2025 throughout the pre-filing phase and the application phase to notify interested constituents of the comment period, in-person scoping session schedule, and associated deadlines on social media outlets like Facebook, Instagram, and X.
-
Created a dedicated project website to inform the public of participation opportunities.
-
Supported FERC’s Office of Energy Projects during the Pre-Filing phase of the project by attending in-person Open House Events January 27 and March 5, 2025, and Scoping sessions held March 24, 2025 – April 3, 2025.
-
Met with local community leaders who traveled to Washington, D.C. to meet with OPP staff to discuss the project.
-
Staff met with community members in cities along the pipeline route prior to and during Open House Events January 27 and March 5, 2025, and Scoping sessions held March 24, 2025 – April 3, 2025 to discuss environmental concerns related to the project and how to participate.
-
Informed the public on the projects transition from the Pre-Filing phase to the application phase. The projects were assigned FERC Docket Nos. CP25-514-000 for Mississippi Crossing Project and CP25-517-000 South System Expansion 4 Project. Encouraged the public to eSubscribe to the new dockets to stay informed.
-
Staff sent out a letter through the USPS mail notifying landowners that the Applicant filed a formal certificate application marking the transition from the Pre-Filing phase in Docket No. PF25-2-000 to the formal application phase in Docket Nos. CP25-517-000 and CP25-517-001.
-
Staff sent a letter through the USPS mailing informing the public of the Notice of Schedule for the Final Order for the Mississippi Crossing Project and the South System Expansion 4 and the Draft Environmental Impact Statement.
-
Staff sent an email to the public notifying them of the Notice of Schedule for the Final Order for the Mississippi Crossing Project and the South System Expansion 4 and the Draft Environmental Impact Statement.
-
Staff sent an email to the public notifying them of the Notice of Schedule for the Final Order for the Mississippi Crossing Project and the South System Expansion 4 and the Draft Environmental Impact Statement.
-
Staff mailed letters to affected landowners and stakeholders about the release of the Draft Environmental Impact Statement (DEIS), including the schedule for all eleven public comment sessions organized by FERC staff
-
OPP staff attended the Draft EIS comment sessions from February 23, 2026 – March 11, 2026, in Mississippi, Alabama, and Georgia.
How to Contact
| Company Website | Contact the Company | Landowner Communication |
|---|---|---|
| Mississippi Crossing Project | Contact Us | Energy Infrastructure/Solutions | Kinder Morgan |
|
Quick Links
- How to eSubscribe
- WorkshOPP: FERC’s Role in Regulating the Construction of Interstate Natural Gas Transmission Pipeline Projects
- WorkshOPP on Filing Comments
- Participating Online at FERC
- How to Seek Rehearing
- How to Contact FERC
- How to Intervene
- How to File a Comment
- How to eFile Comments
- FAQs
- Priority Projects
Contact Information
-
FERC Online SupportEmail: [email protected]
-
News MediaEmail: [email protected]