On September 24, 2026, FERC staff approved Coastal Bend LNG Development LLC’s (CBLNG) request to enter into FERC’s Pre-filing Environmental Review Process (Pre-filing Process) for the planned Coastal Bend LNG Project. CBLNG will construct the LNG Facilities at the Enbridge Ingleside Energy Center (EIEC), an industrial-zoned property in Ingleside, Texas, in San Patricio County. The EIEC is located on the Corpus Christi Ship Channel.

More information may be found in FERC Docket No PF26-13-000 in FERC's eLibrary. 

Please note that this project has not been approved or authorized and requires FERC approval through this process.

Coastal Bend LNG Project Route and Facilities

Coastal Bend Project Map

The Project is a planned LNG liquefaction, storage, and export terminal in Ingleside, Texas. 

According to the applicant, The Project will include four liquefaction trains producing a total of 19.2 mtpa of LNG, along with all necessary utility and auxiliary infrastructure, which will be owned, constructed, and operated by CBLNG. 

CBLNG plans to develop the LNG Facilities at the Enbridge Ingleside Energy Center, securing required leases, easements, and usage rights, including access to Docks 4 and 5. CBLNG will own and operate all LNG Facilities and expects to contract with Enbridge subsidiaries for loading and maritime services. 

Pre-filing Environmental Review Process 

Pre-filing is a “pre-application” phase in the overall environmental review process for interstate natural gas or liquefied natural gas projects under FERC’s jurisdiction. The Pre-filing Process is designed to identify and address environmental aspects of the project before an official application is filed. The Pre-filing Process was established to encourage early involvement by stakeholders during the design and/or routing of an interstate natural gas project.

During the Pre-filing Process, members of the public will have multiple opportunities to get involved and express their views, concerns, and issues. Those opportunities include public comment periods, applicant-sponsored open houses, and scoping sessions hosted by FERC. These opportunities will be posted in FERC’s eLibrary in Docket No. PF26-13-000.

More Information and Staying Updated

You may learn more about the Project through FERC’s eLibrary. When searching for the Project, please enter Docket No. PF26-13-000 in the “Enter Docket Number” text box. FERC’s Office of Public Participation provides an educational video and demonstration on using eLibrary: WorkshOPP and Demonstration: FERC’s eLibrary. 

There is one docket associated with this Project:   

  • The Pre-Filing Docket: Docket No. PF26-13-000

Stay Informed:

Follow OPP on its social media channels:  

OPP regularly sends announcements about upcoming participation opportunities and meetings with interested stakeholders and organizations via its social media channels.  

You may also sign up for FERC’s eSubscription service. eSubscription notifies you via email about submittals and issuances on the project. Please visit www.ferc.gov/esubscription.

You are also encouraged to contact OPP staff to learn more about the Project and participation at FERC by email at [email protected] or phone at 202-502-6595. All media inquiries should be directed to [email protected].

Resources

Guides on Public Participation 

Educational Videos 

Tips on Public Participation 

Informational Handouts 


Project Background:

September 24, 2026: FERC accepts Coastal Bend’s prefile request to enter PF for the planned Coastal Bend LNG Project.


Office of Public Participation’s Outreach Corner

The Office of Public Participation (OPP) is authorized to support public participation in FERC proceedings pursuant to Section 319 of the Federal Power Act. OPP coordinates with and provides assistance to members of the public as to participation in, and understanding of, FERC proceedings. OPP provides outreach to community groups, community members, landowners and other interested parties potentially impacted by infrastructure projects. 


How to Contact

Reach the Project TeamPublic EmailMailing Address

Toll-Free Phone: 

800.958.2872

[email protected]PO Box 55186, Houston, TX 77255

This page was last updated on November 13, 2026