Introduction
On October 16, 2026, Transwestern Pipeline Company, LLC (Transwestern) filed a request to use the Federal Energy Regulatory Commission’s (FERC or the Commission) Pre-Filing Process for the planned Springerville Lateral Project in McKinley and Cibola Counties, New Mexico, and Apache County, Arizona. FERC staff approved the request on November 5, 2026.
More information may be found in FERC Docket No PF27-2-000 in FERC's eLibrary.
Please note that this project has not been approved or authorized and requires FERC approval through this process.
Springerville Lateral Project Route and Description
According to Transwestern, the planned project would provide up to approximately 625 million cubic feet per day (MMcf/d) of natural gas capacity, with 210 MMcf/d provided to the Coronado Generating Station and 415 MMcf/d provided to the Springerville Generating Station. The project would include:
- An approximately 124-mile-long, 30-inch-diameter natural gas transmission lateral pipeline from Transwestern’s East Mainline in McKinley County, New Mexico, to Apache County, Arizona
- An approximately 1-mile-long, 16-inch-diameter delivery lateral off the 30-inch-diameter lateral
- An interconnection with El Paso Natural Gas Company, LLC’s northern mainline in McKinley County, New Mexico
- A new compressor station in Cibola County, New Mexico
- Three meter stations: Continental Divide Meter Station, Coronado Meter Station, and Springerville Meter Station
- Modifications to an existing compressor station in Apache County, Arizona
- Associated appurtenant aboveground facilities
More Information and Staying Updated
Pre-filing is a “pre-application” phase in the overall environmental review process for interstate natural gas or liquefied natural gas projects under FERC’s jurisdiction. The Pre-filing Process is designed to identify and address environmental aspects of the project before an official application is filed. The Pre-filing Process was established to encourage early involvement by stakeholders during the design and/or routing of an interstate natural gas project.
During the Pre-filing Process, members of the public will have multiple opportunities to get involved and express their views, concerns, and issues. Those opportunities include public comment periods, applicant-sponsored open houses, and scoping sessions hosted by FERC. These opportunities will be posted in FERC’s eLibrary in Docket No. PF27-2-000.
You may learn more about the Project through FERC’s eLibrary. When searching for the Project, please enter Docket No. PF27-2-000 in the “Enter Docket Number” text box. FERC’s Office of Public Participation provides an educational video and demonstration on using eLibrary: WorkshOPP and Demonstration: FERC’s eLibrary.
There is one docket associated with this Project:
- The Pre-Filing Docket: Docket No. PF27-2-000
Stay Informed
View filings in FERC’s eLibrary under Docket No. PF27-2-000. eSubscribe to the docket to receive filings and issuances by email.
Background
- October 16, 2026: Transwestern files a request to use the Pre-Filing Process
- November 5, 2026: FERC staff approves the pre-filing request and selects Terracon as the third-party contractor
- November 9, 2026: Transwestern Pipeline Company, LLC submits supplemental information regarding Open House dates and locations related to the pre-filing review of the Springerville Lateral Project
How to Contact
| Company Website | Contact the Company |
|---|---|
| Springerville Lateral Pipeline Project | OR 1-800-842-0339 |
Quick Links
- How to eSubscribe
- WorkshOPP: FERC’s Role in Regulating the Construction of Interstate Natural Gas Transmission Pipeline Projects
- WorkshOPP on Filing Comments
- Participating Online at FERC
- How to Seek Rehearing
- How to Contact FERC
- How to Intervene
- How to File an eComment
- How to eFile Comments
- Frequently Asked Questions (FAQs)
- Priority Projects
Contact Information
-
FERC Online SupportEmail: [email protected]
-
News MediaEmail: [email protected]