Commissioner Mark C. Christie Statement
May 24, 2021
Docket No. 
RM18-9-000

I concur with today’s letter order, which grants extensions of the deadline to submit filings to comply with the requirements of Order No. 2222 to ISO-NE. 

As set forth more fully in my April 9, 2021 concurrence in which requests for extension of time related to Order No. 2222 compliance made by MISO, SPP and PJM were granted,[1] I would not have voted for Order No. 2222 had I been on the Commission last September and I dissented this March from approving Order No. 2222-A.[2] 

Like the motions filed by each of MISO[3], SPP[4] and PJM[5] in their requests for extension of time, the motion filed by ISO-NE[6] illustrates the daunting complexities and certain increased costs to consumers, which I referenced in my dissent to Order No. 2222-A and which apply equally to its forebear, Order No. 2222.  The problems and complexities of compliance described in ISO-NE’s Motion are further evidence that implementing Order Nos. 2222 and 2222-A will be far more complicated, far more costly to consumers and far more burdensome to states, public and municipal power authorities, and electric co-operatives, than these orders and many of their supporters acknowledge.

For example, in support of its request for extension, ISO-NE states that “[t]he scale of coordination required to comply with [Order No. 2222] is challenging, particularly across a multi-state footprint in which all but one state has deregulated electricity markets in which customers choose among competitive suppliers.”[7]  ISO-NE notes that it has already had seven formal NEPOOL compliance committee meetings on Order No. 2222 as well as numerous meetings with “key partners and affected parties,” including with the New England Conference of Public Utilities Commissioners, New England’s electric distribution companies, New England’s transmission operators, Host Participant Assigned Meter Readers (HP AMR), and prospective DER Aggregators.[8]  

One of the issues ISO-NE addresses is the complexity of meter reading related to Order No. 2222.  In addressing these complications, ISO-NE notes the potential for increased costs: 

[T]he region’s Order No. 2222 compliance approach would be improved through the development of a meter reading process for DER aggregations that is workable for all affected parties.  In New England, it is typically the Host Participant Assigned Meter Reader—most commonly, the electric distribution company—that performs the meter reading function for the wholesale markets.  While the Host Participant Assigned Meter Readers perform their meter reading function and recoup their costs for doing so pursuant to state tariffs under the jurisdiction of state regulators, ISO-NE performs all wholesale settlement based on the data the Assigned Meter Readers report to ISO-NE.  Because of this, the recovery of any increased costs to Host Participant Assigned Meter Readers resulting from Order No. 2222 implementation must be approved by state regulators.[9]

ISO-NE states that “a number of specific metering-related challenges have arisen, particularly associated with metering and reporting for DER aggregations that include behind-the-meter components.”[10] 

A Meter Reading Working Group (MRWG) presentation to NEPOOL on this issue, cited by ISO-NE in its motion, makes reference to potential upgrades and modifications to systems and infrastructure.[11]  The last substantive slide in this presentation provides a list of “Additional Factors to Consider and Systems Impacted by DER Requirements,” which includes, “costs of additional metering and telecommunications systems” (including “SCADA requirements needed for Operations to ensure safety and reliability of the grid”), “costs of HP AMR System Upgrades to support FERC Order 2222 reporting requirements”, and examples of certain “administrative burdens.”[12]  The last statement on the slide notes that “[t]ime and [c]ost estimates cannot be provided by the MRWG at this time.  Each HP AMR would need to work within their respective operating company to fully understand the FERC Order 2222 Requirements and how those requirements will impact their various meter, billing and settlement systems.”[13]

These concerns embody precisely my point.  As I said in my April 9, 2021 concurrence, in my remarks at the March 18, 2021 Commission Open Meeting at which Order No. 2222-A was approved and in my written dissent to that order, the costs of compliance with both Order Nos. 2222 and 2222-A will be far more substantial than have been recognized and, ultimately, consumers will pay them.  ISO-NE’s Motion, like those of MISO, SPP and PJM before it, offers a preview of what’s coming in terms of the complications and impacts on reliability caused by these orders and the substantial costs that will have to be expended not only to address those threats but to address the complexity of the requirements these orders impose, costs that will be piled on consumers.

Since – at least at this point – the RTOs have no choice but to comply with these orders, I respectfully concur with the letter order granting ISO-NE’s request for extension of time to make its compliance filing.  I also hope that by granting the extension ISO-NE will have more time to try to mitigate some of the potential for reliability problems.  I recognize that these are validly entered orders of the Commission and the RTOs must comply, but I cannot recognize them as in the public interest.

For these reasons, I respectfully concur.

 

[1] Participation of Distributed Energy Resource Aggregations in Markets Operated by Regional Transmission Organizations and Independent System Operators, 175 FERC ¶ 61,013 (2021) (Christie, Comm’r, concurring, available at https://www.ferc.gov/news-events/news/commissioner-mark-c-christie-concurrence-regarding-order-granting-compliance ).

[2] Participation of Distributed Energy Resource Aggregations in Markets Operated by Regional Transmission Organizations and Independent System Operators, Order No. 2222, 172 FERC ¶ 61,247 (2020), order on reh’g, Order No. 2222-A, 174 FERC ¶ 61,197 (2021) (Christie, Comm’r, dissenting, available at https://www.ferc.gov/news-events/news/item-e-1-commissioner-mark-c-christie-dissent-regarding-participation-distributed).

[3] February 17, 2021 Motion of the Midcontinent Independent System Operator, Inc. for Extension of Order No. 2222 Initial Compliance Requirement.

[4] February 18, 2021 Motion for Extension of Time of Southwest Power Pool, Inc.

[5] February 26, 2021 Motion of PJM Interconnection, L.L.C. for Extension of Time to Submit Compliance Filing.

[6] April 16, 2021 Motion of ISO-New England Inc. to Extend the Time Period to Comply with Order No. 2222 (ISO-NE Motion).

[7] Id. at 4-5. 

[8] Id. at 4.

[9] Id. at 5 (emphasis added).

[10] Id

[11] Id. at 6 (citing Presentation of Sue Clary on behalf of the NEPOOL Meter Reader Working Group, available at https://www.iso-ne.com/static-assets/documents/2021/03/2021_03_24_MRWG_A02_Presentation_FERC_Order_2222_Draft.pdf (MRWG Presentation)). 

[12] MRWG Presentation at 14.

[13] Id.

Contact Information


This page was last updated on May 25, 2021