2007 |
Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles |
Compression (HP) |
States |
Filing Date |
Issued Date |
CP07-8 |
Guardian Pipeline, L.L.C. (PF06-21)
G-II: Expansion and Extension |
537.20 |
119.20 |
78,000.00 |
IL, WI |
10/13/06 |
12/14/07 |
CP06-459 |
Transwestern Pipeline Company (PF06-4)
Phoenix Expansion-Phoenix P/L / San Juan '08 Exp |
500.00 |
284.00 |
0.00 |
AZ, NM |
09/15/06 |
11/15/07 |
CP07-411 |
Texas Eastern Transmission, LP
Cedar Bayou Lateral Project |
360.00 |
3.80 |
0.00 |
TX |
06/29/07 |
11/15/07 |
CP07-395 |
Wyoming Interstate Company, Ltd.
Medicine Bow Expansion Project |
330.00 |
0.00 |
24,930.00 |
WY |
06/06/07 |
10/18/07 |
CP06-61 |
North Baja Pipeline, LLC (PF05-14)
LNG Expansion Project (Phase I) |
2,700.00 |
125.60 |
0.00 |
AZ, CA |
02/07/06 |
10/02/07 |
CP07-32 |
Gulf South Pipeline Co. LP (PF06-31)
Southeast Expansion Project |
560.00 |
110.80 |
45,080.00 |
AL, LA, MS |
12/11/06 |
09/28/07 |
CP05-380 |
Point Comfort Pipeline Company, L.P.
(see Calhoun LNG, L.P./CP05-91) |
1,000.00 |
27.60 |
0.00 |
TX |
06/10/05 |
09/20/07 |
CP06-471 |
Elba Express, L.L.C. (see Southern LNG)(PF06-14)
Elba III Project (Phase A and B) |
1,175.00 |
189.00 |
10,000.00 |
GA, SC |
09/29/06 |
09/20/07 |
CP07-44 |
Southeast Supply Header, LLC/SoNat(PF06-28)
SESH Project (add CP07-45 for total proj) |
140.00 |
115.40 |
39,000.00 |
LA, MS |
12/18/06 |
09/20/07 |
CP07-45 |
Southeast Supply Header, LLC (PF06-28)
SESH Project (add CP07-44 for total proj) |
1,000.00 |
154.00 |
23,650.00 |
AL, MS |
12/18/06 |
09/20/07 |
CP07-51 |
Gulfstream Natural Gas System, L.L.C. (PF06-29)
Phase IV Project/HP(add CP07-51 P/L for total) |
155.00 |
0.00 |
45,000.00 |
AL, FL |
12/22/06 |
09/10/07 |
CP07-51 |
Gulfstream Natural Gas System, L.L.C. (PF06-29)
Phase IV Project/P/L (add CP07-51 HP for total) |
0.00 |
17.70 |
0.00 |
FL |
12/22/06 |
09/10/07 |
CP07-27 |
Tuscarora Gas Transmission Company
2008 Expansion Project |
40.00 |
0.00 |
5,731.00 |
CA |
11/30/06 |
07/24/07 |
CP06-455 |
Kinder Morgan Illinois Pipeline LLC
Kinder Morgan Illinois Pipeline Project |
360.00 |
3.10 |
0.00 |
IL |
09/14/06 |
07/17/07 |
CP07-74 |
Sonora Pipeline, LLC (transp LNG) (PF05-15)
Burgos Hub Exp/Imp Proj (Mission/Progreso PL) |
1,000.00 |
28.90 |
0.00 |
TX |
01/31/07 |
07/10/07 |
CP07-3 |
Natural Gas Pipeline Co. of America
Louisiana Line Expansion Project |
200.00 |
4.40 |
35,000.00 |
LA, TX |
10/10/06 |
07/02/07 |
CP06-449 |
Kinder Morgan Louisiana Pipeline LLC (PF06-16)
(see Sabine Pass LNG-CP05-396) |
3,395.00 |
135.30 |
0.00 |
LA |
09/08/06 |
06/22/07 |
CP06-446 |
Gulf South Pipeline Company, LP (PF06-17; 23)
East TX/North LA Exp Loop/MS Exp |
1,700.00 |
241.90 |
110,604.00 |
LA, MS, TX |
09/01/06 |
06/18/07 |
CP06-115 |
Texas Eastern Transmission, LP
TIME II Project |
150.00 |
31.90 |
32,000.00 |
OH, PA |
04/04/06 |
06/08/07 |
CP00-6 |
Gulfstream Natural Gas System, L.L.C.
Phase III Expansion Project |
345.00 |
34.30 |
0.00 |
FL |
08/15/06 |
06/07/07 |
CP07-14 |
Wyoming Interstate Co., Ltd. (PF06-15)
Kanda Lateral and Mainline Expansion Project |
556.00 |
123.00 |
20,620.00 |
UT, WY |
10/23/06 |
06/07/07 |
CP07-41 |
CenterPoint Energy Gas Transmission Co.
Carthage to Perryville Proj/Phase III Exp |
280.00 |
0.00 |
30,000.00 |
LA, TX |
12/15/06 |
05/17/07 |
CP06-433 |
Northern Natural Gas Company
Palmyra North Expansion (see CP06-403) |
44.20 |
2.00 |
0.00 |
IA, KS, NE, SD |
08/29/06 |
05/02/07 |
CP06-452 |
Trunkline Gas Company, LLC
North Texas Expansion/Field Zone Expansion |
510.00 |
58.50 |
27,800.00 |
LA, TX |
09/11/06 |
04/23/07 |
CP07-25 |
Questar Pipeline Company (PF06-18)
Southern System Expansion Project II |
175.00 |
58.60 |
1,200.00 |
UT |
11/21/06 |
04/23/07 |
CP06-354 |
Rockies Express Pipeline LLC (PF06-3)(KM/Sempra)
REX-West Project(see REX-East/CP07-208) |
1,800.00 |
718.00 |
176,930.00 |
CO, KS, MO, NE, WY |
05/31/06 |
04/19/07 |
CP06-401 |
TransColorado Gas Transmission Co. (PF06-20)
Blanco-Meeker Expansion Project |
250.00 |
0.30 |
15,390.00 |
CO, NM |
06/23/06 |
04/19/07 |
CP06-423 |
Questar Overthrust Pipeline Co. (PF06-19)
Wamsutter Expansion Project |
750.00 |
77.30 |
45,000.00 |
WY |
07/19/06 |
04/19/07 |
CP07-28 |
Southern Natural Gas Company |
|
6.80 |
0.00 |
AL |
12/01/06 |
04/16/07 |
CP06-421 |
Transcontinental Gas Pipe Line Corp (PF06-2)
Potomac Expansion Project |
165.00 |
19.80 |
0.00 |
VA |
07/17/06 |
04/12/07 |
CP05-383 |
Algonquin Gas Transmission, LLC |
800.00 |
16.40 |
0.00 |
MA |
06/13/05 |
03/16/07 |
CP06-335 |
Maritimes & Northeast Pipeline, L.L.C. (PF05-17)
Phase IV Expansion (II) |
418.00 |
1.70 |
88,906.00 |
MA, ME |
05/16/06 |
02/21/07 |
CP06-403 |
Northern Natural Gas Company (PF06-7)
Northern Lights Expansion Project (see CP06-433) |
374.00 |
67.20 |
0.00 |
IA, MN |
06/23/06 |
02/21/07 |
CP06-13 |
Gulf LNG Pipeline, LLC (LNG Clean Energy Project)
(see Gulf LNG Energy, LLC/CP06-12) |
1,500.00 |
5.00 |
0.00 |
MS |
10/28/05 |
02/16/07 |
CP06-34 |
Transcontinental Gas Pipe Line Corp.
Leidy to Long Island Expansion (PF05-6) |
|
0.00 |
0.00 |
NJ, NY, PA |
10/20/06 |
01/11/07 |
|