Commissioner James Danly Statement
April 20, 2023
Docket No. EL22-34-001

For the same reasons that I expressed in my original statement,[1] I further dissent from this order denying rehearing of the Commission’s decision to eliminate transmission organization membership incentives from the rates of American Electric Power Service Corporation affiliates Ohio Power Company (Ohio Power) and AEP Ohio Transmission Company Inc. (AEP Ohio Transmission).[2]  As I previously explained, the Federal Power Act does not limit incentives to only those utilities that “voluntarily” join a transmission organization.[3]  The Commission improperly added this non-statutory requirement in Order No. 679.[4]  We had no authority to do so then or now.  Nothing on rehearing changes my opinion.

I concur with the majority’s determination on rehearing that the American Transmission Systems, Inc., and Duke Energy Ohio, LLC, should continue to collect the transmission organization incentive in rates because these incentives were included in comprehensive settlements.[5]  I would add the further rationale that section 219(c) of the Federal Power Act requires it, and the subsequent addition of the “voluntariness” requirement was a Commission invention not authorized by the statute, as discussed in my original statement.[6]

For these reasons, I respectfully concur in part and dissent in part.

 

[1] Off. of the Ohio Consumers’ Counsel v. Am. Elec. Power Serv. Corp., 181 FERC ¶ 61,214 (2022) (Danly, Comm’r, concurring in part and dissenting in part).

[2] Off. of the Ohio Consumers’ Counsel v. Am. Elec. Power Serv. Corp., 181 FERC ¶ 61,214.

[3] See id. PP 60-63, 83.

[4] See Promoting Transmission Investment through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057, at P 331 (2006), order on reh’g, Order No. 679-A, 117 FERC ¶ 61,345 (2006), order on reh’g, 119 FERC ¶ 61,062 (2007).

[5] Off. of the Ohio Consumers’ Counsel v. Am. Elec. Power Serv. Corp., 181 FERC ¶ 61,214 at PP 60, 64-66.

[6] See id. (Danly, Comm’r, concurring in part and dissenting in part at PP 1-5).