Commissioner Richard Glick Statement
April 16, 2020
Docket No. CP17-101-001
Order: C-3
Dissent in Part Regarding Transcontinental Gas Pipe Line Company, LLC, Northeast Supply Enhancement Project
I dissent in part from todayâs order on rehearing because I believe that the Commissionâs action violates both the Natural Gas Act1
(NGA) and the National Environmental Policy Act2
(NEPA). The Commission once again refuses to consider the consequences its actions have for climate change. Although neither the NGA nor NEPA permit the Commission to assume away the climate change implications of constructing and operating this project, that is precisely what the Commission is doing here.
In todayâs order, the Commission denies rehearing of its order authorizing Transcontinental Gas Pipe Line Companyâs (Transco) proposed Northeast Supply Enhancement Project (Project),3
and continues to treat greenhouse gas (GHG) emissions and climate change differently than all other environmental impacts.4
The Commission again refuses to consider whether the Projectâs contribution to climate change from GHG emissions would be significant, even though it quantified the direct GHG emissions from the Projectâs construction and operation.5
That failure forms an integral part of the Commissionâs decisionmaking: The refusal to assess the significance of the Projectâs contribution to the harm caused by climate change is what allows the Commission to misleadingly state that the Projectâs environmental impacts âwill be reduced to less-than-significant levels,â6
and, as a result, conclude that the Project is required by the public convenience and necessity.7
Claiming that a project has no significant environmental impacts while at the same time refusing to assess the significance of the projectâs impact on the most important environmental issue of our time is not reasoned decisionmaking.
Making matters worse, the Commission again refuses to make a serious effort to assess the indirect effects of the Project. The United States Court of Appeals for the District of Columbia Circuit (D.C. Circuit) has repeatedly criticized the Commission for its stubborn refusal to identify and consider the reasonably foreseeable GHG emissions caused by the downstream combustion of natural gas transported through an interstate pipeline. But even so, todayâs order doubles down on approaches that the D.C. Circuit has already rejected. So long as the Commission refuses to heed the courtâs unambiguous directives, I have no choice but to dissent.
I. The Commissionâs Public Interest Determination Is Not the Product of Reasoned Decisionmaking
We know with certainty what causes climate change: It is the result of GHG emissions, including carbon dioxide and methane, released in large quantities through the production, transportation, and consumption of fossil fuels, including natural gas. The Commission recognizes this relationship, finding, as it must, that climate change is âdriven by accumulation of GHG in the atmosphereâ and that emissions from the Projectâs construction and operation, in combination with emissions from other sources, would âcontribute incrementally to future climate change impacts.â8
In light of this undisputed relationship between anthropogenic GHG emissions and climate change, the Commission must carefully consider the Projectâs contribution to climate change, both in order to fulfill NEPAâs requirements and to determine whether the Project is required by the public convenience and necessity.9
Todayâs order on rehearing falls short of that standard. As part of its public interest determination, the Commission must examine the Projectâs impact on the environment and public safety, which includes the facilitiesâ impact on climate change.10
That is now clearly established D.C. Circuit precedent.11
And yet the Commission continues to insist that it need not consider whether the Projectâs contribution to climate change is significant because, without a âwidely accepted standard,â itâsimply putââcannot.â12
However, the most troubling part of the Commissionâs rationale is what comes next. Based on this alleged inability to assess significance, the Commission concludes that the Projectâs impacts will generally be reduced to âless-than-significantâ levels.13
Think about that. The Commission is simultaneously stating that it cannot assess the significance of the Projectâs impact on climate change, while concluding that all environmental impacts are acceptable to the public interest.14
That is unreasoned and an abdication of our responsibility to give climate change the âhard lookâ that the law demands.15
It also means that the Projectâs impact on climate change does not play a meaningful role in the Commissionâs public interest determination, no matter how often the Commission assures us that it does. Using the approach in todayâs order, the Commission will always conclude that a project will not have a significant environmental impact irrespective of that projectâs actual GHG emissions or those emissionsâ impact on climate change. If the Commissionâs conclusion will not change no matter how many GHG emissions a project causes, those emissions cannot, as a logical matter, play a meaningful role in the Commissionâs public interest determination. A public interest determination that systematically excludes the most important environmental consideration of our time is contrary to law, arbitrary and capricious, and not the product of reasoned decisionmaking.
Commissioner McNamee argues that the D.C. Circuit cases cited above16
were wrongly decided.17
Although that is his prerogative, it is irrelevant to the task before us. As he has explained, we are called on to apply the law and the facts, not our personal policy preferences. But surely, implicit in that statement, is a recognition that we must apply the law as it is, not as we wish it were. The D.C. Circuit has unambiguously interpreted the âpublic convenience and necessityâ standard in section 7 of the NGA to encompass the authority to consider and, if appropriate, act upon âthe direct and indirect environmental effectsâ of a proposed pipeline.18
As Commissioners, our job is to apply that law, not to attack binding judicial precedent in favor of an interpretation that was, in fact, expressly rejected by the court.19
II. The Commissionâs NEPA Analysis of the Projectâs Contribution to Climate Change Is Deficient
The Commissionâs NEPA analysis is similarly flawed. When conducting a NEPA review, an agency must consider both the direct and the indirect effects of the project under consideration.20
While the Commission quantifies the GHG emissions related to Projectâs construction and operation,21
it fails to consider the indirect GHG emissions resulting from the incremental natural gas capacity facilitated by the Project. The D.C. Circuit has repeatedly instructed the Commission that the GHG emissions caused by the reasonably foreseeable combustion of natural gas transported through a pipeline are an indirect effect and must, therefore, be included within the Commissionâs NEPA analysis.22
It is past time for the Commission to learn that lesson.
Beginning with Sabal Trail, the D.C. Circuit has held unambiguously that the Commission must identify and consider reasonably foreseeable downstream GHG emissions as part of its NEPA analysis.23
Shortly after that decision, the Commission attempted to cabin Sabal Trail to its facts, taking the position that it was required to consider downstream GHG emissions only under the exact facts presented in Sabal Trailâi.e., where the pipeline was transporting natural gas for combustion at a particular natural gas power plant (or plants).24
In Birckhead, the D.C. Circuit rejected that argument, admonishing the Commission that it must examine the specific record before it and that it may not categorically ignore a pipelineâs downstream emissions just because it does not fit neatly within the facts of Sabal Trail. Indeed, the Court expressly rejected the Commissionâs argument âthat downstream emissions are an indirect effect of a project only when the projectâs âentire purposeâ is to transport gas to be burned at âspecifically-identifiedâ destinationsââi.e., the facts of Sabal Trail.25
Since Birckhead, the court has continued to turn aside the Commissionâs efforts to ignore reasonably foreseeable downstream GHG emissions.26
Nevertheless, the Commission refuses to calculate or consider the downstream GHG emissions that will likely result from natural gas transported by the Project. Instead, the Commission takes the position that if it does not know the specific volume and end-use of the natural gas, any associated GHG emissions are categorically not reasonably foreseeable.27
That is nothing more than a warmed-over version of the policy that the D.C. Circuit rejected in Birckheadâi.e., that the Commission will ignore downstream GHG emissions, without more detailed information on exactly how the gas would be used.28
Todayâs holding means that, almost by definition, the Commission will never consider the GHG emissions resulting from the gas consumption by customers of local distribution companies, even when the record indicates that the gas will be used in combustion, as it does here.29
Under the current set of fact presented in todayâs record, there are plenty of steps that the Commission could take to consider the GHGs associated with the Projectâs incremental capacity if it were actually inclined to take a âhard lookâ at climate change. At a minimum, we know that the vast majority, 97 percent, of all natural gas consumed in the United States is combusted30
âa fact that, on its own might be sufficient to make downstream emissions reasonably foreseeable, at least absent contrary evidence. Moreover, the record here makes this a relatively easy case: The stated purpose for the expansion capacity is to facilitate natural gas consumption by residential and commercial customers in New York City.31
National Grid, which subscribed the Projectâs entire capacity, confirms that its customers, mostly residential, rely on natural gas âfor critical basic needs including home heating, cooking and hot water.â32
Using that information, the Commission could have easily engaged in a little ââreasonable forecastingââ aided by ââeducated assumptionsâââwhich is precisely what NEPA requiresâin order to develop an estimate or a range of estimates of the likely emissions caused by the Project.33
Although quantifying the Projectâs GHG emissions is a necessary step toward meeting the Commissionâs NEPA obligations, simply reporting the volume of emissions is insufficient.34
In Sabal Trail, the court explained that the Commission was required âto include a discussion of the âsignificanceâ ofâ the indirect effects of the Project, including its GHG emissions.35
That makes sense. Identifying and evaluating the consequences that a projectâs GHG emissions may have for climate change is essential if NEPA is to play the disclosure and good government roles for which it was designed.36
But in todayâs order on rehearing, the Commission refuses to provide that discussion or even attempt to assess the significance of the Projectâs GHG emissions or how they contribute to climate change.37
It is hard to see how hiding the ball by refusing to assess the significance of the Projectâs climate impacts is consistent with either of those purposes.
In addition, under NEPA, a finding of significance informs the Commissionâs inquiry into potential ways of mitigating environmental impacts.38
An environmental review document must âcontain a detailed discussion of possible mitigation measuresâ to address adverse environmental impacts.39
âWithout such a discussion, neither the agency nor other interested groups and individuals can properly evaluate the severity of the adverse effectsâ of a project, making an examination of possible mitigation measures necessary to ensure that the agency has taken a âhard lookâ at the environmental consequences of the action at issue. 40
Instead, the Commission continues to insist that it need not assess the significance of the Projectâs GHG emissions because it lacks a âwidely accepted standard,â to âdetermine the significance of the Projectâs GHG emissionsâ 41
But that does not excuse the Commissionâs failure to evaluate these emissions. As an initial matter, the lack of a single methodology does not prevent the Commission from adopting a methodology, even if that methodology is not universally accepted. The Commission has several tools to assess the harm from the Projectâs contribution to climate change, including, for example, the Social Cost of Carbon. By measuring the long-term damage done by a ton of carbon dioxide, the Social Cost of Carbon links GHG emissions to actual environmental effects from climate change, thereby facilitating the necessary âhard lookâ at the Projectâs environmental impacts that NEPA requires. Especially when it comes to a global problem like climate change, a measure for translating a projectâs climate change impacts into concrete and comprehensible terms plays a useful role in the NEPA process by putting the harms from climate change in terms that are readily accessible for both agency decisionmakers and the public at large. The Commission, however, continues to ignore the tools at its disposal, relying on deeply flawed reasoning that I have previously critiqued at length.42
Regardless of tools or methodologies available, the Commission also can use its expertise to consider all factors and determine, quantitatively or qualitatively, whether the Projectâs GHG emissions have a significant impact on climate change. That is precisely what the Commission does in other aspects of its environmental review. Consider, for example, the Commissionâs findings that the Project will not have a significant effect on issues as diverse as âsoils,â43
âmigratory bird habitat,â44
and âfisheries.â45
Notwithstanding the lack of any standard or âuniversally accepted methodologyâ to assess these impacts, the Commission managed to use its judgment to conduct a qualitative review, and assess the significance of the Projectâs effect on those considerations. The Commissionâs refusal to, at the very least, exercise similar qualitative judgment to assess the significance of GHG emissions here is arbitrary and capricious.46
That refusal is even more mystifying because NEPA âdoes not dictate particular decisional outcomes.â47
NEPA ââmerely prohibits uninformedârather than unwiseâagency action.ââ48
In other words, taking the matter seriouslyâand rigorously examining a projectâs impacts on climate changeâdoes not necessarily prevent any Commissioner from ultimately concluding that a project meets the public interest standard.
Even if the Commission were to determine that a projectâs GHG emissions are significant, that would not be the end of the inquiry nor would it mean that the project is not in the public interest. Instead, the Commission could require mitigationâas the Commission often does with regard to other environmental impacts. The Supreme Court has held that, when a project may cause potentially significant environmental impacts, the relevant environmental impact statement must âcontain a detailed discussion of possible mitigation measuresâ to address adverse environmental impacts.49
The Court explained that, â[w]ithout such a discussion, neither the agency nor other interested groups and individuals can properly evaluate the severity of the adverse effectsâ of a project, making an examination of possible mitigation measures necessary to ensure that the agency has taken a âhard lookâ at the environmental consequences of the action at issue.50
The Commission not only has the obligation to discuss mitigation of adverse environmental impacts under NEPA, but also the authority to condition certificates under section 7 of the NGA,51
which could encompass measures to mitigate a projectâs GHG emissions.
Furthermore, a rigorous examination and determination of significance regarding climate change impacts would bolster any finding of public interest by providing the Commission a more complete set of information necessary to weigh benefits against adverse effects. By refusing to assess significance, however, the Commission short circuits any discussion of mitigation measures for the Projectâs GHG emissions, eliminating a potential pathway for us to achieve consensus on whether the Project is consistent with the public interest.
Todayâs order on rehearing is not the product of reasoned decisionmaking. Its analysis of the Projectâs contribution to climate change is shoddy and its conclusion that the Project will not have any significant environmental impacts is illogical. After all, the Commission itself acknowledges that the Project will contribute to climate change, but refuses to consider whether that contribution might be significant before proclaiming that the Project will have no significant environmental impacts. So long as that is the case, the record simply cannot support the Commissionâs conclusion that there will be no significant environmental impacts. Simply put, the Commissionâs analysis of the Projectâs consequences for climate change does not represent the âhard lookâ that the law requires.
For these reasons, I respectfully dissent in part.
- 11 15 U.S.C. § 717f (2018).
- 22 National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321 et seq.
- 33 Transcontinental Gas Pipe Line Company, LLC, 167 FERC ¶ 61,110 (2019) (Certificate Order), order on rehâg, 171 FERC ¶ 61,031 (2020) (Rehearing Order).
- 44 See Rehearing Order, 171 FERC ¶ 61,031 at PP 26, 29.
- 55 Northeast Supply Enhancement Project Final Environmental Impact Statement (EIS) at 4-309 â 4-310 & Tables 4.10.1-4 & 4.10.1-5; see Certificate Order, 161 FERC ¶ 61,314 at P 90.
- 66 Certificate Order, 167 FERC ¶ 61,110 at P 29.
- 77 Id. P 91.
- 88 EIS at 4-387, 4-389.
- 99 Section 7 of the NGA requires that, before issuing a certificate for new pipeline construction, the Commission must find both a need for the pipeline and that, on balance, the pipelineâs benefits outweigh its harms. 15 U.S.C. § 717f. Furthermore, NEPA requires the Commission to take a âhard lookâ at the environmental impacts of its decisions. See 42 U.S.C. § 4332(2)(C)(iii); Balt. Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 462 U.S. 87, 97 (1983). This means that the Commission must consider and discuss the significance of the harm from a pipelineâs contribution to climate change by actually evaluating the magnitude of the pipelineâs environmental impact. Doing so enables the Commission to compare the environment before and after the proposed federal action and factor the changes into its decisionmaking process. See Sierra Club v. FERC, 867 F.3d 1357, 1374 (D.C. Cir. 2017) (Sabal Trail) (âThe [FEIS] needed to include a discussion of the âsignificanceâ of this indirect effect.â); 40 C.F.R. § 1502.16 (a)â(b) (An agencyâs environmental review must âinclude the environmental impacts of the alternatives including the proposed action,â as well as a discussion of direct and indirect effects and their significance. (emphasis added)). Commissioner McNamee argues that the Commission can consider a projectâs direct GHG emissions in its public convenience and necessity determination (while ignoring the projectâs indirect GHG emissions) without actually determining whether the GHG emissions are significant. Rehearing Order, 171 FERC ¶ 61,031 (McNamee, Commâr, concurring at P 15). This argument defies logic and reason and has no basis in a proceeding entirely devoid of even the affectation that the Commission is factoring the Projectâs GHG emissions in its decisionmaking.
- 1010 See Sabal Trail, 867 F.3d at 1373 (explaining that the Commission must consider a pipelineâs direct and indirect GHG emissions because the Commission may âdeny a pipeline certificate on the ground that the pipeline would be too harmful to the environmentâ); see also Atl. Ref. Co. v. Pub. Serv. Commân of N.Y., 360 U.S. 378, 391 (1959) (holding that the NGA requires the Commission to consider âall factors bearing on the public interestâ).
- 1111 See Allegheny Def. Project v. FERC, 932 F.3d 940, 945-46 (D.C. Cir. 2019), rehâg en banc granted, judgment vacated, 2019 WL 6605464 (D.C. Cir. Dec. 5, 2019); Birckhead v. FERC, 925 F.3d 510, 518-19 (D.C. Cir. 2019); Sabal Trail, 867 F.3d at 1371-72.
- 1212 See EIS at 4-389 â 4-390 (explaining that âwe cannot determine whether the NESEâs Projectâs contribution [to cumulative impacts on climate change] would be significant,â because âthere is no widely accepted standard, per international, federal, or state policy, or as a matter of physical science, to determine the significance of the Projectâs GHG emissionsâ).
- 1313 See, e.g., EIS at ES-14; see also Certificate Order, 167 FERC ¶ 61,110 at P 29 (noting EIS conclusion that the Projectâs adverse environmental impacts will be reduced to less than significant levels through implementation of certain mitigation measures).
- 1414 Certificate Order, 167 FERC ¶ 61,110 at P 91.
- 1515 E.g., Myersville Citizens for a Rural Cmty., Inc. v. FERC, 783 F.3d 1301, 1322 (D.C. Cir. 2015) (â[A]gencies cannot overlook a single environmental consequence if it is even âarguably significant.â); see Michigan v. EPA, 135 S. Ct. 2699, 2706 (2015) (âNot only must an agencyâs decreed result be within the scope of its lawful authority, but the process by which it reaches that result must be logical and rational.â (internal quotation marks omitted)); see also Motor Vehicle Mfrs. Assân, Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983) (explaining that agency action is âarbitrary and capricious if the agency has . . . entirely failed to consider an important aspect of the problem, [or] offered an explanation for its decision that runs counter to the evidence before the agencyâ).
- 1616 Supra notes 10-11.
- 1717 See Rehearing Order, 171 FERC ¶ 61,031 (McNamee, Commâr, concurring at PP 13-14).
- 1818 E.g., Sabal Trail, 867 F.3d at 1373.
- 1919 Id.; see Birckhead, 925 F.3d at 519 (explaining that in âthe pipeline certification context the Commission does have statutory authority to actâ on the reasonably foreseeable GHG emissions caused by the pipeline (citing Sabal Trail, 867 F.3d at 1373)).
- 2020 40 C.F.R. §§ 1502.16(b), 1508.8(b); Sabal Trail, 867 F.3d at 1371.
- 2121 See supra note 5.
- 2222 See Allegheny Def. Project, 932 F.3d at 945-46; Birckhead, 925 F.3d at 518-19; Sabal Trail, 867 F.3d at 1371-72.
- 2323 Sabal Trail, 867 F.3d at 1371-72; see also id. at 1371 (âEffects are reasonably foreseeable if they are âsufficiently likely to occur that a person of ordinary prudence would take [them] into account in reaching a decision.ââ (quoting EarthReports, Inc. v. FERC, 828 F.3d 949, 955 (D.C. Cir. 2016))).
- 2424 Birckhead, 925 F.3d at 518-19 (rejecting the âCommission[âs] conten[tion] [that Sabal Trail] . . . is narrowly limited to the facts of that caseâ (internal quotation marks omitted)).
- 2525 Id. at 519 (citing the Commissionâs brief in that case).
- 2626 See Allegheny Def. Project, 932 F.3d at 945-46 (holding that the petitioners are âcorrect that NEPA required the Commission to consider both the direct and indirect environmental effects of the Project, and that, despite what the Commission argues, the downstream greenhouse-gas emissions are just such an indirect effectâ).
- 2727 Rehearing Order, 171 FERC ¶ 61,031 at P 26.
- 2828 See id. The Commission notes that Birckhead held that downstream GHG emissions are not categorically reasonably foreseeable. Id. P 25. Thatâs true. But the fact that the Commission does not have to consider downstream GHG emissions in every case hardly explains why it was justified in ignoring those emissions in this particular case. See Calvert Cliffsâ Coordinating Comm., Inc. v. U.S. Atomic Energy Commân, 449 F.2d 1109, 1122 (D.C. Cir. 1971) (âNEPA compels a case-by-case examination . . . of discrete factors.â) (quoted in Birckhead, 925 F.3d at 519)..
- 2929 See infra P 11.
- 3030 U.S. Energy Info. Admin., September 2019 Monthly Energy Review 22, 97 (2019) (reporting that, in 2018, 778 Bcf of natural gas had a non-combustion use compared to 29,956 Bcf of total consumption), https://www.eia.gov/totalenergy/data/monthly/archive/00351908.pdf; see also Jayni Hein et al., Institute for Policy Integrity, Pipeline Approvals and Greenhouse Gas Emissions 25 (2019) (explaining that, in 2017, 97% of all natural gas consumed was combusted).
- 3131 See Certificate Order, 167 FERC ¶ 61,110 at P 90; EIS at ES-1, 1-3, 1-15 (explaining that the purpose and need of the Project is to provide incremental interstate pipeline transportation service to Brooklyn Union Gas Company and KeySpan Gas East Corporation to serve National Gridâs residential and commercial customers in New York City, ensure diverse sources of natural gas supply, and improve system reliability); Transco Certificate Application at 14 (noting National Gridâs forecast of need for additional natural gas supply to meet âresidential and commercial demands due to population and market growth within its service territory,â in particular âbeginning in the 2019/2020 heating season because current forecast models . . . indicate an increasing peak day demand year over yearâ). And none of the Projectâs alleged benefitsâimproved reliability and access to economic supplies of natural gasâwill occur unless the natural gas is actually used, and that use will largely (if not entirely) entail combustion.
- 3232 See Certificate Order, 167 FERC ¶ 61,110 (LaFleur, Commâr concurring at P 3) (explaining that the record contains detailed information on downstream end use from both Transco and National Grid, including National Gridâs confirmation that âits customers, mostly residential, rely on natural gas âfor critical basic needs including home heating, cooking and hot waterââ); see also National Gridâs April 2, 2019 Filing at 1.
- 3333 Sabal Trail, 867 F.3d at 1374 (quoting Del. Riverkeeper Network v. FERC, 753 F.3d 1304, 1310 (D.C. Cir. 2014)); see id. (âWe understand that emission estimates would be largely influenced by assumptions rather than direct parameters about the project, but some educated assumptions are inevitable in the NEPA process. And the effects of assumptions on estimates can be checked by disclosing those assumptions so that readers can take the resulting estimates with the appropriate amount of salt.â (internal citations and quotation marks omitted)).
- 3434 See Ctr. for Biological Diversity, 538 F.3d at 1216 (âWhile the [environmental document] quantifies the expected amount of CO2 emitted . . . , it does not evaluate the âincremental impactâ that these emissions will have on climate change or on the environment more generally . . . .â); Klamath-Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt., 387 F.3d 989, 995 (9th Cir. 2004) (âA calculation of the total number of acres to be harvested in the watershed is a necessary component . . . , but it is not a sufficient description of the actual environmental effects that can be expected from logging those acres.â).
- 3535 Sabal Trail, 867 F.3d at 1374.
- 3636 See, e.g., Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 349 (1989) (explaining that one of NEPAâs purposes is to ensure that ârelevant information will be made available to the larger audience that may also play a role in both the decisionmaking process and the implementation of that decisionâ); Lemon v. Geren, 514 F.3d 1312, 1315 (D.C. Cir. 2008) (âThe idea behind NEPA is that if the agencyâs eyes are open to the environmental consequences of its actions and if it considers options that entail less environmental damage, it may be persuaded to alter what it proposed.â).
- 3737 Rehearing Order, 171 FERC ¶ 61,031 at PP 24-27, 29-30; see also Certificate Order, 167 FERC ¶ 61,110 at P 90 (omitting any discussion of the significance of the environmental impact from the Projectâs GHG emissions except to note Transcoâs indication that the Project âwould more than offset net GHG emissions under a hypothetical scenarioâ).
- 3838 40 C.F.R. § 1502.16 (2018) (NEPA requires an implementing agency to form a âscientific and analytic basis for the comparisonsâ of the environmental consequences of its action in its environmental review, which âshall include discussions of . . . [d]irect effects and their significance.â).
- 3939 Robertson, 490 U.S. at 351
- 4040 Id. at 352.
- 4141 See supra note 12.
- 4242 See, e.g.,Transcontinental Gas Pipe Line Co., LLC, 167 FERC ¶ 61,110 (2019) (Glick, Commâr, dissenting in part at P 6 & n.11) (noting that the Social Cost of Carbon âgives both the Commission and the public a means to translate a discrete projectâs climate impacts into concrete and comprehensible termsâ); Fla. Se. Connection, LLC, 164 FERC ¶ 61,099 (2018) (Glick, Commâr, dissenting).
- 4343 EIS at 4-22.
- 4444 EIS at 4-85 â 4-86, 5-9; see also id. at 4-64 & 4-68 (noting that recovery of forested wetlands âmay take up to 30 years or more,â but concluding that the Project would not result in significant impact on wetland resources). Notwithstanding the lack of any âwidely accepted standardâ as to this particular environmental impact, the Commission still uses its judgment to conduct a qualitative review of the Projectâs impact on bird habitat.
- 4545 Id. at 4-119.
- 4646 After all, the standard the Commission typically uses for evaluating significance is whether the adverse impact would result in a substantial adverse change in the physical environment. See e.g. Adelphia Gateway Project Environmental Assessment, Docket No. CP18-46-000 at 33 (Jan 1, 2019). Surely that standard is open to some subjective interpretation by each Commissioner. What todayâs order does not explain is why it is appropriate to exercise subjective interpretation and judgment when it comes to impacts such as soils, migratory bird habitat, and fisheries, but not climate change.
- 4747 Sierra Club v. U.S. Army Corps of Engineers, 803 F.3d 31, 37 (D.C. Cir. 2015).
- 4848 Id. (quoting Robertson, 490 U.S. at 351).
- 4949 Robertson,490 U.S. at 351.
- 5050 Id. at 352; see also 40 C.F.R. §§ 1508.20 (defining mitigation), 1508.25 (including in the scope of an environmental impact statement mitigation measures).
- 5151 15 U.S.C. § 717f(e); Certificate Order, 167 FERC ¶ 61,110 at P 91 (â[T]he Commission has the authority to take whatever steps are necessary to ensure the protection of environmental resources . . . , including authority to impose any additional measures deemed necessary . . . .â).