Hydrokinetic Pilot Project Licensing Procedures: Post-Filing Activity graphic.

Post-Filing Activity

  1. Applicant Files License Application (Including Revised Monitoring Plan), Applicant Prepared DBA, CZMA Application, and 401 Application (if needed). [15 days]
    • Commission Issues Acceptance & REA Notice; and Request for Interventions. [30 days]
    • Commission Issues BA.
  2. Agencies and Others File Recommendations, Conditions, and Comments on the Application. [60 days]
  3. Commission Issues Single EA if FONSI. [30 days]
  4. Agencies and Others Comment on EA. 10J Resolution
  5. Ready for Commission Decision.