D.C. Cir. Nos. 25-1144, et al. Order denying complaint of solar and wind projects in PSCo interconnection queue, that PSCo is improperly conducting interconnection studies by setting aside transmission capacity for PSCo’s own, unqueued generation resources.  Salsa Solar Energy, LLC v. Public Service Co. of Colo., 190 FERC ¶ 61,108 (2025), order on reh’g, 192 FERC ¶ 61,067 (2025).