D.C. Cir. No. 20-1330
Order denying complaint in part (on NGL’s supply arrangements, Phillips 66 proprietary interconnection, and Phillips Pipeline’s prorationing policy), and setting remaining issues (challenging Phillips Pipeline’s transmix rates and practices) for hearing.  NGL Supply Wholesale, LLC v. Phillips 66 Pipeline LLC and Phillips 66 Co., 172 FERC ¶ 61,106 (2020).
 

This page was last updated on May 14, 2021