D.C. Cir. No. 21-1192, et alOrder denying complaint, alleging that New York ISO and Central Hudson failed to use reasonable efforts in processing Hecate’s interconnection request for its project, by applying an “inclusion practice” regarding the firmness of generator interconnection requests.  Hecate Energy Greene County 3 LLC v. Central Hudson Gas & Electric Corp., 176 FERC ¶ 61,023 (2021), order on reh’g, 177 FERC ¶ 61,121 (2021).

This page was last updated on February 26, 2024