No. 16-1342 (D.C. Cir. filed 9/30/2016) Assignment of costs of constructing network upgrade to interconnecting generator, based on tariff language and cost allocation policy; which version of PJM tariff to use. PJM Interconn., L.L.C., 153 FERC ¶ 61,327 (2015), order on reh'g, compl. clar., 156 FERC ¶ 61,090 (2016) (on remand from West Deptford Energy v. FERC, D.C. Cir. 2014). Status: petition for review denied 6/8/2018

This page was last updated on September 14, 2020