No. 18-1298 (D.C. Cir. filed 11/2/2018)

Order rejecting proposed revisions to BG&E formula transmission rate, seeking to recover previously-incurred tax amounts. PJM Interconnection, L.L.C., 161 FERC ¶ 61,163 (2017), order on reh’g & clar., 164 FERC ¶ 61,173 (2018).
 

Status Update

  1. Status: oral argument 10/17/2019 petition for review denied on 3/27/2020

This page was last updated on May 13, 2020