D.C. Cir. No. 20-1249, et al.
Order accepting planning procedures of PJM Transmission Owners, to apply to a limited subset of Supplemental Projects designed to mitigate the risk associated with critical transmission stations and substations identified pursuant to NERC reliability standard CIP-014-2 — Physical Security. Appalachian Power Co. and PJM Interconnection, L.L.C., Order Accepting Tariff Revisions, 170 FERC ¶ 61,196 (2020), order on reh’g, 173 FERC ¶ 61,157 (2020).