Contents of an Application


Traditional and Alternative Licensing Processes

The contents of an application will vary depending on the type of application:

(Note: Most of the links are to external sites and you will be leaving FERC's website)
Project Type
Application Requirements
Major Unconstructed or Major Modified (more than 5 MW) (4.40) External Link 4.32(a) External Link - general information; 4.41(a)-(h) External Link - content of application; 16.10 External Link - information provided by applicants (relicenses); 4.38(f) External Link for original licenses and 16.8(f) External Link for relicense-documentation of consultation
Major Project - Existing Dam (more than 5 MW) (4.50) External Link 4.32(a) External Link - general information; 4.51(a)-(h) External Link -content of application; 16.10 External Link - information provided by applicants (relicenses); 4.38(f) External Link for original licenses and 16.8(f) External Link for relicense - documentation of consultation
Minor Project (1.5 MW or less), or Major Project--Existing Dam (5 MW or less) (4.60) External Link 4.32(a) External Link -general information; 4.61(b)-(f) External Link - content of application; 16.10 External Link - information provided by applicant (relicenses); 4.38(f) External Link for original licenses and 16.8(f) External Link for relicense - documentation of consultation
Major Unconstructed or Major Modified (more than 1.5 MW but less than 5 MW) (4.60) External Link 4.32(a) External Link - general information; 4.61(b), (c), (e), and (f) External Link - content of application; 4.41(f) External Link - environmental report; 16.10 External Link - information provided by applicant (relicenses); 4.38(f) External Link for original licenses and 16.8(f) External Link for relicense - documentation of consultation