Approved Major Pipeline Projects (2009-Present)
Data as of December, 2018
These items include major projects that add capacity. The items listed do not include abandonments, minor projects that do not include any facilities, projects under the blanket program, storage projects or LNG projects.
Note: The Projects are listed by Issued date
Predefined eLibrary searches
Click on the categories below to view additional information.
|
| 2018 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles of Pipe |
Compression (HP) |
States |
Filing Date |
Issued Date |
| CP15-550-000, CP15-551-000, CP15-551-001, PF15-02-000 |
Venture Global Calcasieu Pass, LLC, TransCameron Pipeline, LLC; Venture Global Calcasieu Pass LNG Terminal and Pipeline Project, TransCameron Pipeline Project, Venture Global Calcasieu Pass LNG Terminal |
2,125.00 |
42.70 |
0 |
LA |
06/28/16 |
12/20/18 |
| CP18-06-000 |
RH energytrans, LLC, Risberg Line Project |
55.00 |
59.90 |
1,862 |
PA, OH |
10/16/17 |
12/07/18 |
| CP18-26-000 |
Texas Eastern Transmission, LP, Lambertville East Expansion Project |
60.00 |
0.00 |
7,000 |
NJ |
12/07/17 |
11/16/18 |
| CP18-479-000 |
Portland Natural Gas Transmission System, Phase II of the Portland XPress Project |
11.32 |
0.00 |
0 |
MA, ME |
05/07/18 |
11/13/18 |
| CP18-251-000 |
Portland Natural Gas Transmission System, Presidential Permit Amendment |
39.84 |
0.00 |
0 |
NH, ME, MA |
04/20/18 |
10/26/18 |
| CP18-37-000, CP18-38-000 |
Sierrita Gas Pipeline LLC, Compressor Expansion Project, Presidential Permit Amendment |
748.94 |
0.00 |
15,900 |
AZ |
12/21/17 |
10/01/18 |
| CP17-458-000, PF17-03-000 |
Cheniere Midstream Holdings, Inc., Midship Pipeline Company, LLC, Midcontinent Supply Header Interstate Pipeline Project |
1,440.00 |
233.30 |
118,400 |
OK |
11/09/16 |
08/13/18 |
| CP17-490-000 |
Transcontinental Gas Pipe Line Company, Rivervale South to Market Project |
190.00 |
0.61 |
0 |
NJ |
08/31/17 |
08/10/18 |
| CP17-490-000 |
Transcontinental Gas Pipe Line Company, Rivervale South to Market Project |
190.00 |
0.61 |
0 |
NJ |
08/31/17 |
08/10/18 |
| CP18-108-000 |
Florida Southeast Connection, LLC, Acquisition of Riviera Lateral |
384.00 |
38.00 |
10,500 |
FL |
03/09/18 |
08/06/18 |
| CP18-24-000 |
Steel Reef Pipelines US LLC Border Crossing |
30.00 |
0.05 |
0 |
ND |
12/8/17 |
08/06/18 |
| CP18-108-000 |
Florida Southeast Connection, LLC, Acquisition of Riviera Lateral |
384.00 |
38.00 |
105.00 |
FL |
03/09/18 |
08/06/18 |
| CP17-40-000, CP17-40-001 |
Spire STL Pipeline LLC, Spire STL Pipeline |
400.00 |
65.00 |
0 |
IL, MO |
04/21/17 |
08/03/18 |
| CP17-80 |
Columbia Gas Transmission, LLC, Eastern Panhandle Expansion Project |
47.50 |
3.37 |
0 |
PA, WV |
03/15/17 |
07/19/18 |
| CP18-10-000 |
Texas Eastern Transmission, LP TX-LA Markets Project |
157.50 |
0.00 |
0 |
LA, TX |
10/19/17 |
07/19/18 |
| CP18-35-000 |
Tennessee Gas Pipeline Company, L.L.C., Presidential Permit Amendment |
283.00 |
0.00 |
0 |
TX |
12/20/17 |
07/05/18 |
| CP18-36-000 |
Tennessee Gas Pipeline Company, L.L.C., Presidential Permit Amendmentt |
100.0 |
0.00 |
0 |
TX |
12/20/17 |
07/05/18 |
| CP17-463-000 |
Florida Southeast Connection, LLC Okeechobee Lateral |
400.00 |
5.20 |
0.00 |
FL |
06/14/17 |
05/30/18 |
| CP17-476-000 |
Gulf South Pipeline Company, LP Westlake Expansion Project |
200.00 |
0.30 |
10,000 |
LA |
07/20/17 |
05/17/18 |
| CP17-471-000, PF17-2-000 |
Paiute Pipeline Company Paiute 2018 Expansion Project |
5.64 |
8.46 |
0.00 |
NV |
07/05/17 |
05/15/18 |
| CP17-56, CP17-57 |
Brazoria Interconnector Gas Pipeline LLC, Texas Eastern Transmission, LP, Stratton Ridge Expansion Project |
322.00 |
0.50 |
12,500 |
TX |
02/03/17 |
04/06/18 |
| CP17-8 |
Florida Gas Transmission Company, LLC, East-West Project |
275.00 |
24.70 |
0.00 |
LA, TX |
10/31/16 |
04/05/18 |
| CP17-409, PF17-1 |
DTE Midstream Appalachia, LLC, Birdsboro Pipeline Project |
79.00 |
13.19 |
0.00 |
PA |
05/01/17 |
03/15/18 |
CP15-499-000
CP15-499-001
CP17-26
|
Texas Eastern Transmission, LP, South Texas Expansion,
Pomelo Connector, LLC,
Pomelo Connector Pipeline |
400.00
400 |
0.00
14.00 |
16,800
5,000 |
TX |
05/21/15
12/22/16 |
02/15/18 |
| CP17-46 |
Southern Natural Gas Company, L.L.C., Fairburn Expansion Project |
343.16 |
26.2 |
18,000 |
GA |
02/3/17 |
02/15/18 |
| CP17-257 |
WBI Energy Transmission, Inc., Valley Expansion Project |
40.9 |
37.3 |
3,000 |
MN, ND |
04/26/17 |
02/15/18 |
| CP17-15 |
Dominion Energy Cove Point LNG, LP,
Eastern Market Access |
294 |
0.00 |
31,370 |
MD, VA |
11/15/16 |
01/23/18 |
| CP15-558 |
PennEast Pipeline Company, LLC , Penn East Pipeline |
1,107 |
118.1 |
47,700 |
NJ, PA |
09/25/15 |
01/19/18 |
| CP17-58 |
Transcontinental Gas Pipe Line Company, LLC,
St. James Supply Project |
161.5 |
0.72 |
0.00 |
LA |
02/06/17 |
01/18/18 |
|
| 2017 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles of Pipe |
Compression (HP) |
States |
Filing Date |
Issued Date |
CP16-357 CP16-361 |
Columbia Gas Transmission, LLC,
Columbia Gulf Transmission, LLC, Mountaineer/Gulf Xpress |
2,700 860 |
170.10 0.00 |
215,800 269,900 |
WV, KY, MS, TN |
04/29/16 |
12/29/17 |
| CP16-496 |
Tennessee Gas Pipeline Company, L.L.C. ,
Lone Star Project |
300 |
0.00 |
31,415 |
TX |
08/19/16 |
12/15/17 |
| CP16-486 |
Millennium Pipeline Company, L.L.C.,
Eastern System Upgrade |
223.0 |
7.8 |
44,800 |
NY |
07/29/16 |
11/29/17 |
| CP17-464 |
Rover Pipeline LLC,
Majorsville Compressor 3 |
100 |
0.00 |
3,550 |
WV |
05/17/17 |
11/28/17 |
| CP16-494 |
Transcontinental Gas Pipe Line Company, LLC,
Gulf Connector Expansion |
475 |
0.00 |
30,650 |
TX |
08/16/16 |
11/21/17 |
| CP17-22 |
Kinder Morgan Louisiana Pipeline LLC,
Sabine Pass Expansion |
600 |
1.57 |
47,700 |
LA |
12/13/16 |
11/20/17 |
| CP16-38 |
Columbia Gas Transmission, LLC,
WB Xpress |
1,300 |
29.20 |
186,383 |
VA, WV |
12/30/15 |
11/17/17 |
| CP16-488 |
Natural Gas Pipeline Company of America LLC,
Gulf Coast Expansion Project |
460 |
0.76 |
15,900 |
TX |
08/01/16 |
11/08/17 |
| CP17-9 |
ANR Pipeline Company,
Wisconsin South Expansion |
230.95 |
0.54 |
6,130 |
IL, WI |
11/03/16 |
11/02/17 |
| CP17-19 |
Valley Crossing Pipeline, LLC.,
Border Crossing Project |
2,600 |
0.19 |
0.00 |
TX |
11/21/16 |
10/23/17 |
| CP17-019-000 |
Valley Crossing Pipeline, LLC Border Crossing Project |
2,600.00 |
0.19 |
0.00 |
TX |
11/21/16 |
10/23/17 |
| CP15-554 |
Atlantic Coast Pipeline, LLC (PF15-6)
Atlantic Coast Pipeline Project |
1,500.00 |
564.10 |
117,545.00 |
NC, VA, WV |
10/31/14 |
10/13/17 |
| CP15-554 |
Atlantic Coast Pipeline, LLC, Atlantic Coast Pipeline and Supply Header Projects,
Atlantic-Piedmont Capacity Lease |
0.00 |
35.6 |
12,800 |
NC, VA, WV |
09/18/15 |
10/13/17 |
CP16-10 CP16-13 |
Mountain Valley Pipeline LLC, Equitrans, L.P. Mountain Valley, and Equitrans Expansion |
2,000 600 |
301 7.87 |
171,600 31,300 |
VA, WV
PA, WV |
10/23/15 |
10/13/17 |
| CP16-478 |
Gulf South Pipeline Company, LP,
St. Charles Parish Expansion |
133.33 |
0.17 |
5,000 |
LA |
07/11/16 |
10/06/17 |
| CP16-478-000 |
Gulf South Pipeline Company, LP St. Charles Parish Expansion Project |
133.33 |
0.17 |
5,000.00 |
LA |
07/11/16 |
10/06/17 |
| CP17-28 |
Eastern Shore Natural Gas Company,
2017 Expansion |
61.16 |
39.6 |
3,750 |
DE, PA, MD |
12/30/16 |
10/04/17 |
| CP16-493-000 |
Columbia Gas Transmission, LLC Central Virginia Connector Project |
45.00 |
0.12 |
2,080.00 |
VA |
08/12/16 |
09/06/17 |
| CP16-493 |
Columbia Gas Transmission, LLC ,
Central Virginia Connector |
45 |
0.12 |
2,080 |
VA |
08/12/16 |
09/06/17 |
CP16-22 CP16-23 |
NEXUS Gas Transmission, LLC, Texas Eastern Transmission, LP, Nexus Project |
1,500 950.16 |
255.9 4.74 |
130,000 28,200 |
MI, OH OH |
11/20/15 |
08/25/17 |
| CP16-473-000 |
Texas Eastern Transmission, LP Bayway Lateral Project |
300.00 |
0.44 |
0.00 |
NJ |
06/29/16 |
07/03/17 |
| CP17-062-000 |
Gulf South Pipeline Company, LP |
23.50 |
0.00 |
4,734 |
TX |
02/22/17 |
05/24/17 |
| CP16-474-000 |
High Point Gas Transmission, LLC Abandonment by Sale |
|
|
|
LA |
07/01/16 |
04/04/17 |
| CP15-115 |
National Fuel Gas Supply Corp/Empire Pipeline, Inc. (PF14-18)
Northern Access 2016 Project |
497.00 |
99.80 |
27,564.00 |
NY, PA |
03/17/15 |
02/03/17 |
| CP15-138 |
Transcontinental Gas Pipe Line Co., LLC (PF14-8)
Atlantic Sunrise Project |
1,700.00 |
196.50 |
132,000.00 |
MD, NC, PA, SC, VA |
03/31/15 |
02/03/17 |
| CP16-4-000 |
Tennessee Gas Pipeline Company, L.L.C The Orion Project. |
135.00 |
12.91 |
0.00 |
PA |
10/09/15 |
02/02/17 |
| CP15-93 |
Rover Pipeline LLC (PF14-14 ) Rover Pipeline Project (see Panhandle/CP15-94 and Trunkline/CP15-96) |
3,250.00 |
511.50 |
213,420.00 |
OH, PA, WV |
02/20/15 |
02/02/17 |
| CP15-94 |
Panhandle Eastern Pipe Line Company, LP Panhandle Backhaul Project (see Rover/CP15-93; Trunkline/CP15-96) |
750.00 |
0.00 |
0.00 |
IN, IL, MI, OH |
02/23/15 |
02/02/17 |
| CP15-96 |
Trunkline Gas Company, LLC Trunkline Backhaul Project (see Rover/CP15-93; Panhandle/CP15-94) |
750.00 |
0.00 |
0.00 |
IL, MS, TN |
02/23/15 |
02/02/17 |
| CP16-4 |
Tennessee Gas Pipeline Company, L.L.C.
Orion Project |
135.00 |
12.90 |
0.00 |
PA |
10/09/15 |
02/02/17 |
| CP16-98 |
Dominion Carolina Gas Transmission, LLC (PF15-29)
Transco to Charleston Project |
80.00 |
60.00 |
7,600.00 |
SC |
03/09/16 |
02/02/17 |
| CP16-472 |
Northern Natural Gas Company (PF15-33)
Northern Lights 2017 Expansion |
75.90 |
4.80 |
15,900.00 |
MN |
06/24/16 |
01/31/17 |
| CP16-9 |
Algonquin Gas Transmission, LLC & Maritimes & Northeast Pipeline, L.L.C. (PF15-12 ) Atlantic Bridge Project |
239.00 |
6.30 |
26,500.00 |
CT, MA, NY |
10/22/15 |
01/25/17 |
| CP15-514 |
Columbia Gas Transmission, LLC (PF14-23)
Leach Xpress Project |
1,530.00 |
160.70 |
143,800.00 |
OH, PA, WV |
06/08/15 |
01/19/17 |
| CP15-539 |
Columbia Gulf Transmission, LLC
Rayne Express Expansion |
621.00 |
0.00 |
51,800.00 |
KY |
07/29/15 |
01/19/17 |
|
| 2016 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles of Pipe |
Compression (HP) |
States |
Filing Date |
Issued Date |
| CP15-520 |
Tennessee Gas Pipeline Company, L.L.C.
Triad Expansion Project |
180.00 |
7.00 |
0.00 |
PA |
06/19/15 |
12/30/16 |
| CP14-518 |
Golden Pass Pipeline LLC (PF13-14) |
2,500.00 |
3.00 |
121,750.00 |
TX |
07/07/14 |
12/21/16 |
| CP16-3 |
Texas Eastern Transmission, LP (PF15-17)
Access South/Adair Southwest/Lebanon Extension |
622.00 |
15.80 |
16,875.00 |
KY, OH, MS |
10/08/15 |
12/21/16 |
| CP16-12 |
Tennessee Gas PipelineCompany, L.L.C.
Southwest Louisiana Supply Project |
295.00 |
3.80 |
18,400.00 |
LA |
10/26/15 |
12/15/16 |
|
CP16-17 |
Millennium Pipeline Company, L.L.C. (PF15-23)
Valley Lateral Project
|
130.00 |
7.80 |
0.00 |
NY |
11/13/15 |
11/09/16 |
| CP16-27 |
Paulsboro Natural Gas Company LLC |
20.00 |
2.60 |
0.00 |
PA |
12/01/15 | 09/07/16 |
| CP15-148 |
Tennessee Gas Pipeline Company, L.L.C.
Susquehanna West Project |
145.00 |
8.10 |
4,500.00 |
PA |
04/02/15 |
09/06/16 |
| CP15-77 |
Tennessee Gas Pipeline Company, L.L.C.
Broad Run Expansion Project |
200.00 |
0.00 |
130,021.00 |
KY, TN. WV |
01/30/15 |
09/06/16 |
| CP15-492 |
Dominion Transmission, Inc.
Leidy South Project |
155.00 |
0.20 |
45,835.00 | MD, PA, VA |
05/15/15 |
08/29/16 |
| CP15-117 |
Transcontinental Gas Pipe Line Co., LLC (PF14-10)
Dalton Expansion Project |
448.00 |
115.00 |
21,830.00 | GA, NC, VA |
03/19/15 |
08/03/16 |
| CP15-18-000;001 |
Eastern Shore Natural Gas Company
White Oak Mainline Expansion Project |
45.00 |
5.40 |
3,550.00 | PA |
11/21/14 |
07/21/16 |
| CP15-118 |
Transcontinental Gas Pipe Line Company, LLC
Virginia Southside Expansion Project II |
250.00 |
4.30 |
46,830.00 | NC, SC, VA |
03/23/15 |
07/07/16 |
| CP15-527 |
Transcontinental Gas Pipe Line Company, LLC
NY Bay Expansion Project |
115.00 |
0.20 |
15,640.00 | NJ, NY, PA |
07/08/15 |
07/07/16 |
| CP15-517 |
Gulf South Pipeline Company, LP (PF15-4)
Coastal Bend Header Project |
1,420.00 |
66.00 |
136,445.00 |
TX |
10/30/14 |
06/20/16 |
| CP15-504 |
Dominion Carolina Gas Transmission, LLC
Columbia to Eastover Project
|
18.00 |
28.00 |
0.00 |
SC |
05/29/15 |
06/02/16 |
| CP14-115 |
Elba Express Company, L.L.C. (PF13-3)
see Elba Liquefaction/Southern LNG (CP14-103)
|
769.00 |
0.00 |
126,300.00 |
GA |
03/21/14 |
06/01/16 |
| CP14-493 |
Southern Natural Gas Company, L.L.C.
Zone 3 Expansion Project
|
235.00 |
3.30 |
8,700.00 |
AL, GA |
05/30/14 |
06/01/16 |
| CP16-35 |
First Midstream, LLC
|
152.00 |
16.60 |
0.00 |
PA |
12/18/15 |
06/01/16 |
| CP15-503 |
Comanche Trail Pipeline, LLC
San Elizario Crossing Project
|
1,100.00 |
0.20 |
0.00 |
TX |
05/29/15 |
05/19/16 |
| CP15-500 |
Trans-Pecos Pipeline, LLC
Presidio Crossing Project
|
1,300.00 |
0.20 |
0.00 |
TX |
05/28/15 |
05/05/16 |
| CP15-525 |
UGI Sunbury, LLC (PF15-9)
Sunbury Pipeline Project
|
200.00 |
34.40 |
0.00 |
PA |
07/01/15 |
04/29/16 |
| CP14-497 |
Dominion Transmission, Inc.
New Market Project
|
112.00 |
0.00 |
33,023.00 |
NY |
06/02/14 |
04/28/16 |
| CP14-511 |
Kinder Morgan Louisiana Pipeline LLC
Lake Charles Expansion Proj (see Magnolia LNG CP14-347)
|
1,400.00 |
1.30 |
64,000.00 |
LA |
06/30/14 |
04/15/16 |
| CP15-8 |
Northwest Pipeline LLC
Kalama Lateral Project
|
320.00 |
3.10 |
0.00 |
WA |
10/27/14 |
04/11/16 |
| CP15-102 |
Rockies Express Pipeline LLC
Seneca Lateral Facilities Section 311 Conversion
|
600.00 |
14.70 |
15,980.00 |
OH |
03/02/15 |
04/07/16 |
| CP15-89 |
Transcontinental Gas Pipe Line Company, LLC
Garden State Expansion Project
|
180.00 |
0.00 |
50,500.00 |
NJ |
02/18/15 |
04/07/16 |
| CP15-144 |
Florida Gas Transmission Company, LLC
Jacksonville Expansion Project
|
15.00 |
8.70 |
5,000.00 |
FL |
03/31/15 |
03/30/16 |
| CP15-493 |
El Paso Natural Gas Company, L.L.C.
Monument 90 Presidential Permit
|
42.60 |
0.00 |
0.00 |
AZ |
05/19/15 |
03/30/16 |
| CP15-513 |
Texas Gas Transmission, LLC
Northern Supply Access Project
|
384.00 |
0.00 |
33,565.00 |
IN, KY, LA, OH, TN |
06/05/15 |
03/24/16 |
| CP15-505 |
Natural Gas Pipeline Company of America LLC
Chicago Market Expansion Project
|
238.00 |
0.00 |
30,000.00 |
IL |
06/01/15 |
03/17/16 |
| CP14-529 |
Tennessee Gas Pipeline Company, L.L.C.
Connecticut Expansion Project
|
72.10 |
13.30 |
0.00 |
CT, MA, NY |
07/31/14 |
03/11/16 |
| CP15-137 |
Rockies Express Pipeline LLC
REX Zone 3 Capacity Enhancement Project
|
800.00 |
0.00 |
156,657.00 |
IN, OH |
03/31/15 |
02/25/16 |
| CP14-554 |
Florida Southeast Connection, LLC (PF14-2)
FL SE Conn Proj (see Sabal Tr, Tran/Hillabee)
|
640.00 |
126.00 |
0.00 |
FL |
09/26/14 |
02/02/16 |
| CP15-16 |
Transcontinental Gas Pipe Line Co., LLC (PF14-6)
Hillabee Expansion Proj (see Sabal Trail, FL SE Con)
|
1,131.70 |
43.50 |
88,500.00 |
AL |
11/04/14 |
02/02/16 |
| CP15-17 |
Sabal Trail Transmission LLC (PF14-1)
SE Mkt P/L Proj (see FL SE Conn,Tran/Hillabee)
|
1,075.00 |
516.20 |
209,900.00 |
AL, FL, GA |
11/21/14 |
02/02/16 |
| CP15-105 |
Texas Gas Transmission, LLC
Western Kentucky Lateral Project
|
230.00 |
22.50 |
0.00 |
KY |
03/04/15 |
01/21/16 |
|
| 2015 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles of Pipe |
Compression (HP) |
States |
Filing Date |
Issued Date |
| CP15-41-000;001 |
Equitrans, L.P. (PF14-13)
Ohio Valley Connector Project
|
850.00 |
36.90 |
36,000.00 |
OH, WV |
12/30/14 |
12/30/15 |
| CP15-7 |
Dominion Transmission, Inc.
Monroe to Cornwall Project
|
205.00 |
0.00 |
12,552.00 |
WV |
10/22/14 |
12/30/15 |
| CP15-87 |
Columbia Gas Transmission, LLC
Utica Access Project
|
205.00 |
5.00 |
0.00 |
WV |
02/12/15 |
12/30/15 |
| CP14-119 |
Trunkline Gas Company, LLC (PF12-8)
Pipeline Modification Project (see Lake Charles LNG Company, LLC/CP14-120)
|
3,100.00 |
17.90 |
119,075.00 |
AR, LA, MS |
03/25/14 |
12/17/15 |
| CP15-523 |
American Midstream (Midla), LLC
Natchez Pipeline Project
|
48.30 |
52.50 |
0.00 |
LA, MS |
06/29/15 |
12/17/15 |
| CP15-90 |
Texas Eastern Transmission, LP
Gulf Markets Expansion Project
|
650.00 |
0.00 |
17,780.00 |
KY, LA, MS, OH, TN, TX |
02/19/15 |
12/17/15 |
| CP14-555 |
Dominion Transmission, Inc.
Lebanon West II Project |
130.00 |
10.10 |
10,915.00 |
OH, PA |
09/30/14 |
11/19/15 |
| CP15-29 |
Transcontinental Gas Pipe Line Company, LLC
Gulf Trace Proj (see Sabine Pass Liq/LNG/CP15-29) |
1,200.00 |
7.00 |
64,000.00 |
LA |
12/15/14 |
10/21/15 |
| CP15-24 |
Dominion Cove Point LNG, LP
Keys Energy Project |
107.00 |
0.00 |
6,000.00 |
MD, VA |
12/03/14 |
10/20/15 |
| CP15-22 |
Dominion Cove Point LNG, LP
St. Charles Transportation Project |
132.00 |
0.00 |
7,000.00 |
MD, VA |
12/03/14 |
10/20/15 |
| CP15-161 |
Roadrunner Gas Transmission, LLC |
875.00 |
0.20 |
0.00 |
TX |
04/09/15 |
10/15/15 |
| CP15-109 |
Columbia Gulf Transmission, LLC (PF14-16)
| 800.00 |
34.10 |
12,260.00 |
LA |
03/16/15 |
09/17/15
|
| CP14-553 |
Texas Gas Transmission, LLC
Ohio-Louisiana Access Project |
626.00 |
0.00 |
10,915.00 |
LA |
09/25/14 |
08/28/15
|
| CP14-496 |
Dominion Transmission, Inc,
Clarington Project |
250.00 |
0.20 |
16,133.00 |
OH, WV |
06/02/14 |
08/19/15 |
| CP15-104 |
DBM Pipeline, LLC
Ramsey Residue Line |
275.00 |
9.00 |
0.00 |
TX |
03/03/15 |
07/24/15
|
| CP14-522 |
Algonquin Gas Transmission, LLC (PF14-5)
Salem Lateral Project |
115.00 |
1.20 |
0.00 |
MA |
07/01/14 |
05/14/15
|
| CP14-513 |
Impulsora Pipeline, LLC |
1,120.00 |
1.20 |
0.00 |
TX |
07/01/14 |
05/14/15
|
CP14-509
CP14-504 |
Paiute Pipeline Company (PF14-4)
2015 Elko Area Expansion Project |
22.00 |
35.20 |
0.00 |
NV |
06/27/14 |
05/14/15
|
| CP13-553 |
Cheniere Creole Trail Pipeline, L.P. (PF13-8)
Liquefaction Exp and P/L Ext and Exp Proj(see Sab(CP13-552) |
1,500.00 |
104.30 |
53,000.00 |
LA |
09/30/13 |
04/06/15
|
| CP15-70 |
Regency Field Services LLC
Beaver Residue Line (acquisition) |
100.00 |
12.50 |
0.00 |
OK |
01/23/15 |
03/23/15 |
| CP14-504 |
Transcontinental Gas Pipe Line
Co., LLC (PF14-3)
Rock Springs Expansion Project |
192.00 |
11.20 |
4,000.00 |
MD, PA |
06/23/14 |
03/19/15 |
| CP14-112 |
Empire Pipeline, Inc./Natnl Fuel
Gas Corp(PF13-12)
Tuscarora Lateral Project (see stge part) |
55.00 |
17.10 |
1,384.00 |
NY, PA |
03/18/14 |
03/10/15 |
| CP14-96 |
Algonquin Gas Transmission, LLC
(PF13-16)
Algonquin Incremental Market (AIM) Project |
342.00 |
37.60 |
81,620.00 |
CT, MA, NY, RI |
02/28/14 |
03/03/15 |
| CP14-70 |
National Fuel Gas Supply
Corporation
West Side Expansion and Modernization Project |
175.00 |
23.00 |
3,550.00 |
PA |
02/06/14 |
03/02/15 |
| CP14-100 |
National Fuel Gas Supply
Corporation LLC
Northern Access 2015 Project |
140.00 |
0.00 |
23,100.00 |
NY |
03/07/14 |
02/27/15 |
| CP14-498 |
Rockies Express Pipeline
LLC
Zone 3 East-to-West Project |
1,200.00 |
0.20 |
0.00 |
IL, IN, OH |
06/10/14 |
02/27/15 |
| CP14-88 |
Tennessee Gas Pipeline Company,
L.L.C.
Niagara Expansion Project |
158.00 |
3.10 |
0.00 |
NY, PA |
02/21/14 |
02/27/15 |
| CP14-97 |
Carolina Gas Transmission
Corporation |
45.00 |
0.20 |
9,500.00 |
SC |
02/28/14 |
02/19/15 |
|
| 2014 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles of Pipe |
Compression (HP) |
States |
Filing Date |
Issued Date |
| CP12-508 |
Cheniere Corpus Christi Pipeline, LP (PF12-3) |
2,250.00 |
23.00 |
53,260.00 |
TX |
08/31/12 |
12/30/14 |
| CP13-551 |
Transcontinental Gas Pipe Line Co., LLC (PF13-5) Leidy Southeast Expansion Project |
525.00 |
30.00 |
71,900.00 |
MD, NC,NJ, PA, VA |
09/30/13 |
12/18/14 |
| CP14-104 |
Texas Eastern Transmission, LP U2GC Project (Uniontown to Gas City Project) |
425.00 |
0.00 |
0.00 |
IN, OH, PA |
03/11/14 |
12/18/14 |
| CP14-17 |
Columbia Gas Transmission, LLC
(PF13-7)
East Side Expansion Project |
312.00 |
19.00 |
31,004.00 |
MD, NJ, NY, PA |
11/01/13 |
12/18/14 |
| CP13-499 |
Constitution Pipeline Company,
LLC (PF12-9) |
650.00 |
124.00 |
0.00 |
NY, PA |
06/13/13 |
12/02/14 |
| CP13-502 |
Iroquois Gas Transmission
System, LP (PF12-9)
(see Constitution P/L/CP13-499) |
0.00 |
|
21,800.00 |
NY |
06/13/13 |
12/02/14 |
| CP14-514 |
ANR Pipeline Company
Sulphur Springs Compressor Project |
133.60 |
0.00 |
10,915.00 |
IN |
07/02/14 |
12/02/14 |
| CP14-68 |
Texas Eastern Transmission, LP
(PF13-15)
OPEN (Ohio Pipeline Energy Network) Project |
550.00 |
75.80 |
18,800.00 |
OH |
01/31/14 |
12/02/14 |
| CP14-21 |
Florida Gas Transmission
Company, LLC
Pompano Compressor Station 21.5 Project |
25.00 |
1.20 |
22,000.00 |
FL |
11/15/13 |
10/30/14 |
| CP14-101 |
City of Clarksville, Tennessee
(PF13-17) |
52.00 |
20.80 |
0.00 |
KY, TN |
03/07/14 |
10/09/14 |
| CP14-123 |
Questar Overthrust Pipeline
Company
Jurisdictional Tap Line (JTL) Project |
60.00 |
2.50 |
0.00 |
WY |
03/26/14 |
10/09/14 |
| CP13-113 |
Dominion Cove Point LNG, LP
(PF12-16)
Cove Point Liquefaction Project (see LNG proj) |
860.00 |
0.00 |
62,500.00 |
VA |
04/01/13 |
09/29/14 |
| CP14-99 |
Columbia Gas Transmission, LLC |
15.70 |
3.40 |
0.00 |
PA |
03/06/14 |
08/22/14 |
| CP14-87 |
Southeast Supply Header,
LLC
SESH Expansion Project |
45.00 |
0.80 |
8,000.00 |
LA |
02/20/14 |
08/14/14 |
| CP14-18 |
Transcontinental Gas Pipe Line
Company, LLC
Woodbridge Delivery Lateral |
264.00 |
2.40 |
0.00 |
NJ |
11/07/13 |
08/11/14 |
| CP13-27 |
Cameron Interstate Pipeline, LLC
(PF12-12)
Cameron Interstate Pipeline Expansion Project |
2,330.00 |
21.00 |
56,820.00 |
LA |
12/14/12 |
06/19/14 |
| CP13-73; 74 |
Sierrita Gas Pipeline LLC
(PF12-11)
Sierrita Pipeline Project |
200.80 |
60.90 |
0.00 |
AZ |
02/07/13 |
06/06/14 |
| CP13-132 |
Transcontinental Gas Pipe Line
Company, LLC
Northeast Connector Project |
100.00 |
0.00 |
16,940.00 |
NJ, PA |
04/09/13 |
05/08/14 |
| CP13-36 |
Transcontinental Gas Pipe Line
Co., LLC (PF09-8)
Rockaway Delivery Lateral Project |
647.00 |
3.20 |
0.00 |
NY |
01/07/13 |
05/08/14 |
| CP13-523 |
Transcontinental Gas Pipe Line
Company, LLC
Mobile Bay South III Expansion Project |
225.00 |
0.00 |
21,500.00 |
AL |
07/18/13 |
04/17/14 |
| CP13-547 |
Equitrans, L.P.
Jefferson Compressor Station Expansion Project |
600.00 |
0.00 |
12,913.00 |
PA |
09/16/13 |
04/11/14 |
| CP14-13 |
Houston Pipe Line Company
LP
Border Crossing Project |
140.00 |
0.10 |
0.00 |
TX |
10/28/13 |
03/20/14 |
|
| 2013 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles of Pipe |
Compression (HP) |
States |
Filing Date |
Issued Date |
| CP13-509 |
DCP Midstream, LP
Lucerne Residue Pipeline
|
230.00 |
7.60 |
0.00 |
CO |
7/1/2013 |
12/27/2013 |
| CP13-477 |
Columbia Gas Transmission, LLC
Smithfield III Expansion Project (see CP13-478)
|
444.00 |
0.00 |
25,000.00 |
PA, WV |
5/10/2013 |
12/19/2013 |
| CP13-498 |
Eastern Shore Natural Gas Company
White Oak Lateral Project
|
55.20 |
5.50 |
0.00 |
DE |
6/13/2013 |
11/27/2013 |
| CP13-30 |
Transcontinental Gas Pipe Line Co., LLC (PF12-15)
Virginia Southside Expansion Project |
270.00 |
98.00 |
21,830.00 |
NC, NJ, VA |
05/25/12 |
11/21/13 |
| CP13-96 |
Gulf South Pipeline Company, LP (PF12-21)
Southeast Market Expansion Project |
510.50 |
70.00 |
34,215.00 |
AL, MS |
03/08/13 |
11/18/13 |
| CP13-482 |
Net Mexico Pipeline Partners, LLC
Net Mexico Border Crossing |
2,100.00 |
0.30 |
0.00 |
TX |
05/20/13 |
11/08/13 |
| CP13-14 |
Millennium Pipeline Company, L.L.C. (PF12-10)
Hancock Compressor Project |
222.50 |
0.10 |
15,900.00 |
NY |
11/01/12 |
10/01/13 |
| CP13-3 |
Tennessee Gas Pipeline Company
Rose Lake Expansion Project |
230.00 |
0.00 |
25,291.00 |
PA |
10/10/12 |
09/19/13 |
| CP13-64 |
Gulf Crossing Pipeline Company, LLC
Panda Power Lateral Project |
125.00 |
16.50 |
0.00 |
TX |
02/01/13 |
09/12/13 |
| CP13-13 |
Dominion Transmission, Inc.
Natrium to Market Project |
185.00 |
0.00 |
7,700.00 |
PA |
11/01/12 |
09/03/13 |
| CP12-516 |
Discovery Gas Transmission LLC
Junction Platform Project |
405.00 |
19.50 |
2.00 |
LA |
09/07/12 |
05/24/13 |
| CP12-496 |
Colorado Interstate Gas Company, L.L.C.
High Plains 2013 Expansion Proj/ Lancaster Lateral |
225.00 |
7.80 |
0.00 |
CO |
08/07/12 |
03/20/13 |
| CP12-494 |
Gas Transmission Northwest LLC (PF11-5)
Carty Lateral Project |
175.00 |
24.30 |
0.00 |
OR |
07/31/12 |
03/14/13 |
| CP12-20 |
Dominion Transmission, Inc.
Sabinsville to Morrisville Project |
92.00 |
3.60 |
0.00 |
PA |
11/21/11 |
03/08/13 |
| CP12-19 |
Dominion Transmission, Inc.
Tioga Area Expansion Project |
270.00 |
15.30 |
0.00 |
NY, PA |
11/21/11 |
03/08/13 |
| CP12-351 |
Cheniere Creole Trail Pipeline Company
Creole Trail Pipeline Expansion Project |
1,530.00 |
0.00 |
53,125.00 |
LA |
04/30/12 |
02/21/13 |
|
| 2012 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles of Pipe |
Compression (HP) |
States |
Filing Date |
Issued Date |
| ONSHORE |
|
|
|
|
|
|
|
| CP12-72 |
Dominion Transmission, Inc. (PF11-9)
Allegheny Storage Project (see stge docket) |
125.00 |
3.10 |
19,550.00 |
MD, OH, PA |
02/17/12 |
12/20/12 |
| CP12-520 |
Gulf Shore Energy Partners, LP
(see CP13-78)
|
100.00 |
0.00 |
2,180.00 |
TX |
09/11/12 |
12/12/12 |
| CP12-30 |
Transcontinental Gas Supply Co., LLC (PF11-4)
Northeast Supply Link Expansion
|
250.00 |
12.50 |
41,000.00 |
NJ, NY, PA |
12/14/11 |
11/02/12 |
| CP12-6 |
El Paso Natural Gas Company
Willcox Lateral 2013 Expansion (see CP12-7)
|
185.00 |
0.10 |
0.00 |
AZ |
10/11/11 |
10/12/12 |
| CP12-468 |
Atlas Pipeline Mid-Continent WestTex, LLC
Pioneer Natural Resources USA, Inc.
|
150.00 |
10.20 |
0.00 |
TX |
05/30/12 |
09/28/12 |
| CP12-50 |
Alliance Pipeline L.P. (PF11-7)
Tioga Lateral Project (see CP13-21)
|
106.50 |
79.30 |
6,000.00 |
ND |
01/25/12 |
09/20/12 |
| CP12-96 |
El Paso Natural Gas Company
Norte Crossing Project
|
366.00 |
0.30 |
0.00 |
TX |
03/22/12 |
08/31/12 |
| CP12-28 |
Tennessee Gas Pipeline Company, L.L.C.
MMP Project
|
240.00 |
7.90 |
0.00 |
PA |
12/09/11 |
08/09/12 |
| CP11-515 |
Millennium Pipeline Company, L.L.C.
Minisink Compressor Project
|
225.00 |
0.20 |
12,260.00 |
NY |
07/14/11 |
07/17/12 |
| CP12-51 |
Bluewater Gas Storage, LLC
|
300.00 |
0.30 |
0.00 |
MI |
01/27/12 |
06/21/12 |
| CP11-161 |
Tennessee Gas Pipeline Company (PF10-23)
Northeast Upgrade Project
|
636.00 |
39.50 |
22,310.00 |
NJ, PA |
03/31/11 |
05/29/12 |
| CP11-56 |
Texas East Tran, LP/Algon Gas Tran, LLC(PF10-17)
NJ-NY Expansion Project
|
800.00 |
20.30 |
0.00 |
NJ, NY |
12/20/10 |
05/21/12 |
| CP11-547 |
Natural Gas Pipeline Company of America LLC
(see storage part of docket)
|
100.00 |
0.00 |
22,000.00 |
IL |
09/20/11 |
05/17/12 |
| CP11-512 |
National Fuel Gas Supply Corporation
Line N 2012 Expansion Project
|
163.00 |
4.80 |
20,620.00 |
PA |
07/08/11 |
03/29/12 |
| CP11-490 |
Columbia Gas Transmission, LLC
|
246.00 |
2.50 |
0.00 |
MD, VA, WV |
05/20/11 |
03/20/12 |
| CP11-549 |
DCP Midstream, LP
LaSalle Residue Line Project
|
230.00 |
11.00 |
0.00 |
CO |
09/23/11 |
02/06/12 |
|
| 2011 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles of Pipe |
Compression (HP) |
States |
Filing Date |
Issued Date |
| CP11-67 |
Texas Eastern Transmission, LP (PF10-21) TEAM 2012 Expansion Project |
190.00 |
17.80 |
20,720.00 |
OH, PA |
01/25/11 |
11/17/11 |
| CP10-480 |
Central New York Oil & Gas Company, LLC MARC I Project |
550.00 |
39.00 |
31,660.00 |
PA |
08/09/10 |
11/14/11 |
| CP11-128 |
National Fuel Gas Supply Corp. (see CP11-133/Tn) Northern Access Expansion Project |
320.00 |
0.00 |
14,210.00 |
NY, PA |
03/07/11 |
10/20/11 |
| CP11-41 |
Dominion Transmission, Inc. Ellisburg to Craigs Project (see CP11-30) |
150.00 |
0.50 |
10,800.00 |
NY, PA |
11/19/10 |
09/15/11 |
| CP11-30 |
Tennessee Gas Pipeline Company Northeast Supply Diversification Project (NSD) (see CP11-41) |
250.00 |
6.80 |
0.00 |
NY, PA |
11/12/10 |
09/15/11 |
| CP11-18 |
Transcontinental Gas Pipe Line Co., LLC (PF10-13) Mid-South Expansion Project |
225.00 |
22.60 |
47,780.00 |
AL, GA, NC |
03/02/09 |
08/25/11 |
| CP11-39 |
Dominion Transmission, Inc. Northeast Expansion Project |
200.00 |
0.00 |
32,440.00 |
PA |
11/18/10 |
08/24/11 |
| CP11-68 |
Equitrans, L.P. (PF10-19) Sunrise Project |
313.60 |
47.00 |
14,205.00 |
PA, WV |
01/27/11 |
07/21/11 |
| CP11-31 |
Transcontinental Gas Pipe Line Co. LLC (PF10-16) Mid-Atlantic Connector Expansion Project |
142.00 |
2.80 |
18,950.00 |
VA |
11/12/10 |
07/01/11 |
| CP10-448 |
Dominion Transmission, Inc. (PF09-15) Appalachian Gateway Project |
484.30 |
107.40 |
17,965.00 |
PA, WV |
06/01/10 |
06/16/11 |
| CP10-493 |
Empire Pipeline, Inc. (PF10-5)
Tioga County Extension Project |
350.00 |
16.40 |
0.00 |
NY, PA |
08/26/10 |
05/19/11 |
| CP11-25 |
Questar Pipeline Company (PF10-7)
ML 104 Extension Project |
160.00 |
24.60 |
0.00 |
UT |
11/10/10 |
05/04/11 |
| CP10-459 |
ETC Tiger Pipeline, LLC ETC Tiger Pipeline Expansion Project |
400.00 |
20.50 |
30,565.00 |
LA |
06/15/10 |
02/03/11 |
| CP10-194 |
Central New York Oil & Gas Company, LLC |
288.00 |
0.00 |
28,700.00 |
NY, PA |
04/27/10 |
01/20/11 |
|
| 2010 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles |
Compression (HP) |
States |
Filing Date |
Issued Date |
| CP10-471 |
Texas Eastern Transmission, LP Hot Spring Lateral Project |
112.00 |
8.40 |
0.00 |
AR |
07/15/10 |
12/16/10 |
| CP10-458 |
National Fuel Gas Supply Corporation (PF10-1) Line N Compressor Installation Proj (see CP10-457) |
150.00 |
1.90 |
4,740.00 |
PA |
06/11/10 |
12/16/10 |
| CP10-468 |
Northern Border Pipeline Company (PF10-2) Princeton Lateral Project |
120.00 |
8.60 |
0.00 |
IL |
07/02/10 |
11/22/10 |
| CP10-89 |
East Tennessee Natural Gas, LLC (PF09-13) Northeastern Tennessee Proj (NET Proj) |
150.00 |
28.10 |
0.00 |
VA, TN |
03/08/10 |
10/25/10 |
| CP10-14 |
Kern River Gas Transmission Co (PF09-7) Apex Expansion Project |
266.00 |
28.00 |
78,000.00 |
NV, UT, WY |
11/02/09 |
09/16/10 |
| CP10-3 |
Questar Overthrust Pipeline Company (PF09-6) Main Line (ML) 133 Loop Expansion Project |
800.00 |
43.30 |
0.00 |
WY |
10/13/09 |
08/31/10 |
| CP10-21 |
Transcontinental Gas Pipe Line Corporation
Mobile Bay South II Expansion Project |
380.00 |
0.0 |
8,180.00 |
AL |
11/16/09 |
07/26/10 |
| CP09-455 (PF08-31) |
Florida Gas Transmission Co
Mobile Bay Lateral Extension Proj(see Transco CP09-456) |
342.60 |
8.80 |
0.0 |
AL |
08/14/09 |
07/15/10 |
| CP09-456 (PF08-32) |
Transcon Gas Pipe Line Cp/FGT Co
Pascagoula Expansion Proj (see FGT/ CP09-455) |
810.00 |
15.50 |
0.0 |
AL, MS |
08/14/09 |
07/15/10 |
| CP10-13 |
Wyoming Interstate Company
2010 System Enhancement Project |
285.00 |
2.40 |
0.0 |
WY |
11/04/09 |
06/25/10 |
CP09-444
(PF09-1) |
Tennessee Gas Pipeline Company /
Line 300 Expansion |
350.0 |
128.7 |
59,158 |
NJ, PA |
07/17/09 |
05/14/10 |
| CP09-464 |
Colorado Interstate Gas Company /
Raton 2010 Expansion Project |
130.0 |
118.6 |
0 |
CO |
09/10/09 |
04/29/10 |
CP09-161
(PF08-23) |
Bison Pipeline LLC /
Bison Pipeline Project |
477.0 |
302.0 |
4,700 |
MT, ND, WY |
04/20/09 |
04/09/10 |
CP09-460
(PF09-9) |
ETC Tiger Pipeline, LLC /
Tiger Pipeline Project |
2,000.0 |
175.0 |
119,680 |
LA, TX |
08/31/09 |
04/07/10 |
CP09-54
(PF08-9) |
Ruby Pipeline, LLC /Ruby Pipeline Project |
1,456.0 |
677.8 |
157,161 |
NV, OR, UT, WY |
01/27/09 |
04/05/10 |
| CP09-449 |
Wyoming Interstate Company, Ltd.
Diamond Mountain Compressor Station Proj |
180.00 |
0.00 |
20,604.00 |
UT |
07/29/09 |
03/26/10
|
| CP09-417 |
Transcontinental Gas Pipe Line Co. LLC
Bayonne Delivery Lateral Project |
250.00 |
0.80 |
0.00 |
NJ |
05/22/09 |
01/08/10
|
| CP09-420 |
Gulf South Pipeline Company, LP
Haynesville/Perryville Expansion Project |
556.00 |
0.80 |
49,471.00 |
LA |
05/22/09 |
01/06/10
|
| CP08-420, et al. |
Algonquin Gas Transmission, LLC, Hubline/East to West Project |
281.5 MMcf/d |
2.6 |
none |
NJ, CT |
06/09/08 |
01/05/10 |
|
| 2009 |
| Docket No. |
Company/Project |
Capacity (MMcf/d) |
Miles |
Compression (HP) |
States |
Filing Date |
Issued Date |
| CP09-433 |
Fayetteville Express Pipeline LLC, Fayetteville Express Pipeline |
2,000 |
184.8 |
71,645 |
AR, MS |
06/15/09 |
12/17/09 |
| CP07-191 |
Port Dolphin Energy LLC/Port Dolphin Project |
1,200 |
3.93 |
0 |
FL |
04/25/07 |
12/03/09 |
| CP09-17 |
Florida Gas Transmission Company, LLC/Phase VIII Expansion Project |
820.0 |
483.2 |
213,600 |
FL,AL |
10/31/08 |
11/19/09 |
CP09-415
(PF08-30) |
Northwest Pipeline GP
Sundance Trail Expansion Project |
150.00 |
15.50 |
10,310.00 |
CO, WY |
05/20/09 |
11/19/09 |
| CP09-68 |
Texas Eastern Transmission, LP/TEMAX and TIME III Projects |
455.0 |
62.0 |
84,433 |
PA |
02/27/09 |
11/19/09 |
| CP09-237 |
Transcontinental Gas Pipe Line Co., LLC
Delta Lateral Project |
208.80 |
3.40 |
0.00 |
PA |
04/30/09 |
10/28/09 |
| CP09-18 |
Dominion Transmission, Inc.
Dominion Hub III Project |
224.30 |
9.40 |
0.00 |
PA, WV |
10/31/08 |
10/06/09 |
| CP09-56 |
Midcontinent Express Pipeline LLC |
300.00 |
0.00 |
32,720.00 |
LA, MS, TX |
01/29/09 |
09/17/09 |
| CP09-57 |
Transcontinental Gas Pipe Line Co., LLC 85 North Expansion Project |
308.50 |
22.00 |
63,925.00 |
AL, GA |
01/30/09 |
09/03/09 |
| CP09-36 and CP09-40 |
Southern Natural Gas Company, et al./South System Expansion III Project |
735 |
81.1 |
42,962 |
GA, MS, AL |
12/15/08 |
08/27/09 |
| CP09-76(PF06-34) |
Questar Overthrust Pipeline Co.
Overthrust Compression Expansion Project |
300.00 |
0.00 |
32,000.00 |
WY |
03/05/09 |
08/03/09 |
| CP09-58
| Rockies Express Pipeline LLC |
200.00 |
0.00 |
38,000.00 |
CO, WY |
02/03/09 |
07/16/09 |
| CP09-47 |
Oasis Pipeline LP and Oasis Pipeline Co. TX LP
Clint Export Project |
600.00 |
0.30 |
0.00 |
TX |
01/14/09 |
06/18/09 |
| CP08-429 |
Kern River Gas Transmission Company
2010 Expansion Project |
145.00 |
0.00 |
20,500.00 |
CA, WY |
06/20/08 |
06/04/09 |
| CP09-11 (PF08-12) |
Northern Natural Gas Company
Northern Lights 2009/10 Zone EF Exp Proj |
136.00 |
52.20 |
15,000.00 |
MN |
10/17/08 |
05/13/09 |
| CP08-476 |
Transcontinental Gas Pipe Line Co. LLC
Mobile Bay South Expansion Project |
253.50 |
0.50 |
9,470.00 |
AL |
09/18/08 |
05/07/09 |
| CP09-29 |
CenterPoint Energy Gas Transmission Co. |
274.00 |
0.00 |
30,000.00 |
LA |
12/05/08 |
04/27/09 |
| CP08-467 |
Texas Gas Transmission, LLC
Fayetteville Shale Compression Project |
2,300.00 |
0.00 |
39,990.00 |
AR, MS |
09/02/08 |
04/16/09 |
| CP08-477 (PF08-8) |
Northwest Pipeline GP
Colorado Hub Connection Project |
582.00 |
27.40 |
0.00 |
CO |
09/24/08 |
04/02/09 |
| CP08-256 |
Algonquin Gas Transmission, LLC
J-2 Loop Project |
140.00 |
2.30 |
0.0 |
MA |
04/30/08 |
02/11/09 |
| CP08-462 |
Algonquin Gas Transmission, LLCKleen Energy Lateral |
131.00 |
1.10 |
0.00 |
CT |
08/15/08 |
02/05/09 |
| CP07-62, et al |
AES Sparrows Point, LLC and Mid-Atlantic Express, LLC/Sparrows Point Project |
1,500 |
88 |
0 |
MD, PA |
01/08/07 |
01/15/09 |
|
|
|
 |
| CONTACT |
General Information
Office of External Affairs
Telephone: 202-502-8004
Toll-free: 1-866-208-3372
Email:
customer@ferc.gov
Note: Comments sent to customer@ferc.gov are not considered an official filing before the Commission or made part of the record. To file an official comment on a proceeding before the Commission, please follow our Rules of Practice at 18 CFR 385 .