Dauphin Island Gathering Partners

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index



Effective Date: 11/01/2010, Docket: RP10-1262-000, Status: Effective

Third Revised Sheet No. 229 Third Revised Sheet No. 229

Superseding: Second Revised Sheet No. 229


of this Section 19.7 in order to establish the basis of

accounting for revenues from an Acquiring Shipper as a means

of preserving the economic basis of the Negotiated Rate.


19.8 Offers to Acquire Firm Capacity:


Transporter agrees to post on its EBB at a party's request offers

to purchase firm capacity on a permanent or temporary basis. All

such parties must have met the Prequalified Bidder Requirements

pursuant to Subsection 19.6(e).


19.9 Timeline for Capacity Releases:


(a) The Capacity Release Timeline applies to all parties

involved in the capacity release process provided that:


(i) all information provided by the parties to the

transaction is valid and the Acquiring Shipper has

been determined to be creditworthy before the capacity

release is tendered;


(ii) for index-based capacity release transactions, the

releasing Shipper has provided the capacity release

service provider with sufficient instructions to

evaluate the corresponding bid(s) according to the

timeline; and


(iii) there are no special terms or conditions to the



Further, the capacity release service provider may complete

the capacity release process on a different timeline if the

offer includes unfamiliar or unclear terms and conditions

(e.g., designation of an index not supported by