CASE MILESTONES FOR LEAD DOCKET NO.: ER14-01183-000

Southwestern Electric Power Company

ASSOCIATED DOCKETS:

DOCKET NO.

APPLICANT
ER14-01184-000 Southwestern Electric Power Company
ER14-01185-000 Southwestern Electric Power Company
ER14-01186-000 Southwestern Electric Power Company
ER14-01187-000 Southwestern Electric Power Company
ER14-01248-000 Southwestern Electric Power Company
ER14-01249-000 Southwestern Electric Power Company
ER14-01250-000 Southwestern Electric Power Company
ER14-01307-000 Southwestern Electric Power Company
ER14-01402-000 Southwestern Electric Power Company

EVENTS:

START END EVENT DESCRIPTION
03/28/2014 03/28/2014 Hearing Order Date
03/28/2014 03/28/2014 Chief Judge Designated
04/15/2014 04/15/2014 Settlement Judge Designated
05/01/2014 05/01/2014 Settlement Conference
05/06/2014 05/06/2014 Status Report
06/19/2014 06/19/2014 Settlement Conference
06/25/2014 06/25/2014 Status Report
08/19/2014 08/19/2014 Status Report


NOTES:

3/28/14 - Order Accepting For Filing, Suspending, and Settling For Hearing Proposed Revised
Power Supply Agreements, Consolidating Proceedings and Establishing Settlement Judge Procedures

4/15/14 - Order of Chief Judge Designating Settlement Judge and Scheduling Settlement
Conference (Judge Cintron; SC 5/1/14 @ 10 am)

5/2/14 - Order of Chief Judge Granting Motion To Intervene Out of Time (Rayburn Country
Electric Cooperative, Inc.)

5/6/14 - Settlement Status Report (SC 6/2/14; recommends SJ procedures cont)

5/13/14 - Order of Chief Judge Continuing Settlement Judge Procedures

5/29/14 - Order Cancelling and Rescheduling Settlement Conference (6/19/14 @ 10 am)

6/25/14 - Settlement Judge Report To The Commission And Chief Judge (parties have reached
settlement in principle; recommend SJ proceduers cont)

8/19/14 - Settlement Judge Report To The Commission And Chief Judge (after this period transpires the settlement will be certified to the Commision., SJ recommend SJ procedures cont)