CASE MILESTONES FOR LEAD DOCKET NO.: ER12-01901-000

Genon Power Midwest, LP

EVENTS:

START END EVENT DESCRIPTION
07/30/2012 07/30/2012 Hearing Order Date
07/30/2012 07/30/2012 Chief Judge Designated
08/06/2012 08/06/2012 Settlement Judge Designated
08/30/2012 08/30/2012 Status Report
09/06/2012 09/06/2012 Settlement Conference
10/11/2012 10/11/2012 Settlement Conference
10/25/2012 10/25/2012 Status Report
11/15/2012 11/15/2012 Settlement Conference
12/27/2012 12/27/2012 Status Report
01/23/2013 01/23/2013 Settlement Conference
03/01/2013 03/01/2013 Settlement Conference
03/05/2013 03/05/2013 Status Report
04/29/2013 04/29/2013 Status Report
05/08/2013 05/08/2013 Settlement Filed
05/28/2013 05/28/2013 Initial Comments On Settlement
06/07/2013 06/07/2013 Reply Comments On Settlement


NOTES:

7/5/13- Report of Contested Settlement

7/10/13 - Errata - Report Of Contested Settlement

7/11/13 - Order of Chief Judge Terminating Settlement Judge Procedures