CASE MILESTONES FOR LEAD DOCKET NO.: ER12-00469-000

PJM Interconnection, L.L.C.

EVENTS:

START END EVENT DESCRIPTION
04/10/2012 04/10/2012 Hearing Order Date
04/11/2012 04/11/2012 Chief Judge Designated
04/16/2012 04/16/2012 Settlement Judge Designated
05/03/2012 05/03/2012 Settlement Conference
05/10/2012 05/10/2012 Status Report
07/09/2012 07/09/2012 Status Report
08/16/2012 08/16/2012 Settlement Filed
09/05/2012 09/05/2012 Initial Comments On Settlement
09/07/2012 09/07/2012 Status Report
09/17/2012 09/17/2012 Reply Comments On Settlement
09/26/2012 09/26/2012 Settlement Uncontested


NOTES:

9/26/12 - Certification of Uncontested Settlement

11/15/12 - Commission issued Letter Order approving settlement