Licensing Processes

Matrix Comparing Three Processes
  Integrated Licensing Process (ILP) Traditional Licensing Process (TLP) Alternative Licensing Process (ALP)
Consultation w/ Resource
Agencies and Indian Tribes
Integrated Paper driven Collaborative
FERC Staff Involvement
- Pre-filing; beginning at filing of NOI- Early and sustained throughout process - Post Application filing - Pre-filing

- Early involvement on requested basis
Deadlines - Defined deadlines for all participants throughout the process, including FERC - Pre-filing - some deadlines for participants

- Post-filing - defined deadlines for participants
- Pre-filing - deadlines defined by collaborative group

- Post-filing - defined deadlines for participants
Study Plan Development - Developed through study plan meetings

- Plan approved by FERC
- Developed by applicant based on early agency and tribal recommendations

- No FERC involvement
- Developed by collaborative group

- FERC staff assist as resources allow
Study Dispute Resolution - Informal dispute resolution available to all participants

- Formal dispute resolution available to agencies w/ mandatory conditioning authority. Three-member panel technical recommendation on study dispute

- OEP Director opinion binding on applicant
- FERC study dispute resolution available upon request

- OEP Director issues advisory opinion
- FERC study dispute resolution available upon request

- OEP Director issues advisory opinion
Application - Preliminary licensing proposal or draft application and final application include Exhibit E that has form and contents of an EA - Draft and final application include Exhibit E - Draft and final application with applicant prepared EA or third-party EIS
Additional Information
Requests
- Available to participants before filing of application

- No additional info requests after application filed
- Available to participants after filing of Application - Available to participants primarily before filing of application

- Post-filing requests available but should be limited due to collaborative approach
Timing of Resource Agency
Terms and Conditions
- Preliminary terms and conditions filed 30 to 60 days after REA notice

- Modified terms and conditions 60 days after comments on draft NEPA document
- Preliminary terms and conditions filed 60 days after REA notice
- Schedule for final terms and conditions
- Preliminary terms and conditions filed 60 days after REA notice

- Schedule for final terms and conditions


LICENSING PROCESSES
Alternative Licensing Process Flowcharts Traditional Licensing Process Flowcharts
 