Revised Study Plan [see 18 CFR 5.13 External Link]


  • From the close of the 90-day comment period on the proposed study plan, the applicant has 30 days to file a revised study plan for Commission approval.
  • The plan must address the study criteria and explain any agreements or continued disagreements over studies.
  • Stakeholders have 15 days to file comments on the revised study plan.