The Integrated Licensing Process (ILP) - Tutorial

Preparing an Application

Study Implementation [see 18 CFR 5.15 External Link]

» Process

  • To ensure that studies are gathering the needed information, applicants must periodically report on the progress of implementing the approved study plan and the data being gathered.
  • The first report is due within one year of the Director's study determination.
  • If multiple years of study are required, subsequent reports are due each year thereafter,
  • The study report(s) should include a description of the overall progress implementing the approved study plan; any variances from the approved study plan; and proposed modifications to the approved study plan (if any).
  • The applicant must hold a meeting with stakeholders within 15 days of filing the report to discuss study results and any proposals to modify the study plan.




CONTACT
David Turner
Telephone: 202-502-6091
Email: david.turner@ferc.gov
 
THE INTEGRATED LICENSING PROCESS (ILP)

Main Page

  • Overview


  • Preparing an Application Processing the License Application
     