Enbridge Pipelines (AlaTenn) L. L. C.
FOURTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/11/2002, Docket: RP03- 40-000, Status: Effective
Original Sheet No. 302 Original Sheet No. 302 : Effective
FORM OF SERVICE CONTRACT (FT)
(continued)
[If facilities are to be constructed, a brief description of the
facilities will be included, as well as who is to construct, own and/or
operate such facilities in accordance with Transporter's Rate Schedule FT].
___________________________________________
___________________________________________
___________________________________________
___________________________________________
ARTICLE V
RECEIPT AND DELIVERY PRESSURES
Shipper shall deliver or cause to be delivered to Transporter the gas to
be transported hereunder at pressures sufficient to deliver such gas into
Transporter's system at the Point(s) of Receipt. Transporter shall deliver
the gas to be transported hereunder to or for the account of Shipper at the
pressures existing in Transporter's system at the Point(s) of Delivery.
ARTICLE VI
QUALITY SPECIFICATIONS AND STANDARDS FOR MEASUREMENT
For all gas received, transported and delivered hereunder the parties
agree to the Quality Specifications and Standards for Measurement as specified
in the General Terms and Conditions of Transporter's FERC Gas Tariff, Fourth
Revised Volume No. 1. To the extent that no new measurement facilities are
installed to provide service hereunder, measurement operations will continue
in the manner in which they have previously been handled. In the event that
such facilities are not operated by Transporter then responsibility for
operations shall be deemed to be Shipper's. Any exceptions to this Article
shall be specified on Exhibits(s) ____________ attached hereto.