Enbridge Pipelines (AlaTenn) L. L. C.
FOURTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/01/2003, Docket: RP00-401-003, Status: Effective
First Revised Sheet No. 60 First Revised Sheet No. 60 : Effective
Superseding: Original Sheet No. 60
RATE SCHEDULE LMS (continued)
3.2 Any request of LMS shall include the information listed below. The
PDA Party shall provide any additional information required by
Transporter to process the request.
(a) Gas Quantities: The PDA Party shall provide the aggregate
Contract Demand for the Delivery or Receipt Point(s)
operated by the PDA Party.
(b) Delivery Point: The location of the Delivery Point(s) that
the PDA Party proposes to be covered by the PDA.
(c) Term: The proposed commencement and termination dates of
service under this Rate Schedule.
(d) Transportation Contract Information: The contract number
and names and addresses of all Shippers that have named any
of the PDA Party's points as Primary Receipt or Delivery
Point(s) and the maximum quantity that may be delivered or
received under each Shipper's firm transportation contract
at each of the PDA Party's point.
(e) Credit Evaluation: All credit information required in the
applicable Rate Schedule.
4. SCHEDULING AND CONFIRMATION BY PDA PARTY
The PDA Party will confirm with Transporter nominations under each FT,
FT-SG or IT Contract that specifies point(s) as a Primary or Secondary
Delivery Point(s). Such confirmation shall provide a ranking of the
markets to be served by gas quantities nominated at the point. The PDA
Party shall notify Shipper and Transporter, within one hour of any
change in nomination by an affected Shipper to confirmed nominations
scheduled for delivery.
5. DAILY VARIANCES
5.1 The daily variance for a Delivery Point PDA shall be the net of
the difference between the total volumes scheduled and confirmed
for delivery at Delivery Points covered by