Enbridge Pipelines (AlaTenn) L. L. C.
FOURTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2005, Docket: RP05-442-000, Status: Effective
First Revised Sheet No. 38 First Revised Sheet No. 38 : Effective
Superseding: Original Sheet No. 38
RATE SCHEDULE FT-SG (continued)
4.3 Change in Receipt and Delivery Point(s): Subject to availability
of Firm Capacity, Shipper may change the Primary Receipt or
Delivery Point(s) under its FT-SG Contract (including
redistributing the Contract Demand amount) on a monthly basis by
an amendment of Exhibits A and/or B to the FT-SG Contract. Such
amendment shall be reflected in an executed revision of Exhibits A
and/or B submitted to Transporter by the twentieth of the month
preceding the month for which the change is desired.
Subject to available capacity, Transporter will allow a change to
designated Receipt Point(s) at any time in the event of failure to
deliver committed gas supplies because of equipment failure,
compressor malfunction, freezing, or similar force majeure
conditions. Transporter will provide, via its Electronic Bulletin
Board ("EBB") and/or Internet Web site notice