Enbridge Pipelines (AlaTenn) L. L. C.

FOURTH REVISED VOLUME NO. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/11/2002, Docket: RP03- 40-000, Status: Effective

Original Sheet No. 29 Original Sheet No. 29 : Effective

 

RATE SCHEDULE FT (Continued)

 

5. RATE AND CHARGES

 

5.1 Applicable Rates: The applicable rates for service under the Rate

Schedule FT are the applicable Maximum Reservation and Commodity

Rates shown on the effective Tariff Sheet No. 4; provided,

however, Transporter has the right at any and from time to time to

adjust the Maximum Reservation and Commodity Rates applicable to

any service upon notice to Shipper to any level not less than the

Minimum or more than the Maximum Reservation and Commodity Rates

established for this Rate Schedule and set forth on the effective

Tariff Sheet No. 4.

 

Transporter shall file with the Commission the reports required

under Section 284.7 of the Commission's Regulations for any

adjustment below the maximum rates service under this Rate

Schedule.

 

Authorized Overrun Quantities: Transportation by Transporter of

Authorized Overrun Quantities shall be at a rate equal to the

current maximum applicable commodity rate for Interruptible

transportation under Rate Schedule IT.

 

5.2 New Facilities Charge: In addition to the charge pursuant to

Section 5.1 of this Rate Schedule, Transporter shall or may, at

its option, subject to Shipper's prior charge Shipper an amount to

recoup the cost of facilities constructed at the Shipper's request

in order to provide transportation service under this Rate

Schedule. Transporter shall not use the amounts so collected in

establishing its general system rates. The applicable New

Facilities Charge shall be stated in the FT Contract.

 

Transporter will construct only those facilities to render

transportation services hereunder which interconnect with

facilities that either cross or are immediately adjacent to

Transporter's existing facilities; provided, however, Transporter

shall not construct facilities hereunder which will result in the

expansion or diminishment Transporter's mainline capacity or which

compromise the operational integrity of Transporter's pipeline

system. Transporter will own and operate all facilities

constructed hereunder.