Enbriidge Pipelines (Midla) L. L. C.
FIFTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2009, Docket: RP09-980-000, Status: Effective
First Revised Sheet No. 179 First Revised Sheet No. 179
Superseding: Original Sheet No. 179
Customer notifies the other party that it desires a special test
of any measuring equipment, Pipeline and Customer shall cooperate
to secure a prompt verification of the accuracy of such equipment.
In the event that a special test is requested by other Pipeline or
Customer and, after test, the equipment is determined to register
no greater than two percent, either high or low, the requesting
party shall pay all costs for said test.
24.3 Correction of Metering Equipment - Any meter found, on test, to
register not more than two percent (2%) high or low shall be
deemed to be correct as to past measurements but shall be
corrected to record accurately. In the event any meter, upon
test, proves to be more than two percent (2%) high or low,
adjustment shall be made to fully correct the readings of such
meters; provided, however, that if the period in which the error
occurred is not known or cannot be agreed upon, then the period
shall be deemed to be either the last half of the time elapsed
since the last test, or the last thirty (30) Days, whichever is
the lesser period. If a meter is out of repair or is being tested
or in the event that Pipeline's meters become inoperative or
manifestly in error and Customer has not installed a check meter
or meters as herein provided, or if such check meters have been
installed and fail accurately to register or are manifestly in
error, then the quantity of Gas delivered during the period
Pipeline's meter or meters were inoperative or manifestly in error
shall be determined by estimating as nearly as possible the
quantity of Gas delivered hereunder during like periods under
similar conditions when such meter was registering accurately or
correctly within the tolerance set forth herein.
24.4 Customer shall be entitled to install and operate at its own
expense near the Point(s) of Delivery such meter or meters of
standard type as shall enable Customer to check the amount of Gas
delivered. If Customer shall exercise this right of installing
and operating check meters, then in the event of failure of
Pipeline's meters to register accurately at any time, the
registration of Customer's check meters shall be taken as the
current quantity of Gas delivered to Customer by