Enbriidge Pipelines (Midla) L. L. C.

FIFTH REVISED VOLUME NO. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/01/2009, Docket: RP09-980-000, Status: Effective

First Revised Sheet No. 164 First Revised Sheet No. 164

Superseding: Original Sheet No. 164

 

15.2 Confirmations

 

(a) The confirmation process shall be initiated by the Pipeline.

 

(b) Customers that are required by this FERC Gas Tariff to

provide nominations shall be responsible for verifying that

nominations have been confirmed and shall be responsible for

ensuring that each affected Point Operator confirms timely

nominations in accordance with the timeline(s) set forth in

Paragraph 15.1.(i) hereof. Customers shall be required to

conform quantities of Gas delivered at a point to such

confirmed nominations.

 

(c) Nominations for which a confirmation is initiated but not

received shall be scheduled by using the lesser of the

confirmation quantity or the previously scheduled quantity

should be the new confirmed quantity.

 

(d) Customers required by this FERC Gas Tariff to provide

nominations shall be required to provide Pipeline with

Customer's or its Agent's address, telephone number, and

facsimile machine number to be available twenty-four (24)

hours a Day, seven (7) Days a week. Customers shall be

required to maintain the appropriate address, telephone

number, and facsimile machine number to be available twenty-

four (24) hours a Day, seven (7) Days a week of all parties

in the confirmation path to the affected Point Operator.

 

(e) Any waiver of any deadline(s) set forth in this Section 15.2

for the transmittal of information or data in any form is at

the sole discretion of the receiving party. Sender of such

information or data may not waive and is bound to adhere to

such deadline(s) unless waiver has been granted by receiving

party.