Enbriidge Pipelines (Midla) L. L. C.
FIFTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2009, Docket: RP09-980-000, Status: Effective
First Revised Sheet No. 131 First Revised Sheet No. 131
Superseding: Original Sheet No. 131
6.4 (a) Should a Customer desire waiver of the capacity curtailment
provisions of Paragraph 6.3(a) during emergency situations
in order to prevent injury to life or property or to provide
minimum plant protection, Pipeline shall retain the right
but not the obligation or duty to provide for an exception
in all or part to its curtailment provisions set forth
herein.
(b) The Customer seeking waiver shall inform Pipeline and
Pipeline shall inform all affected Customers as to the
extent of the situation or emergency giving rise to the
necessity for an exception to the curtailment provisions of
this Section 6 and the measures that have been taken to
reduce the extent of the situation or emergency.
(c) A Customer whose Gas was diverted under this Paragraph 6.4
shall have the option to be compensated for such Gas by the
Customer whose request for emergency relief resulted in a
loss of transportation capacity or the need for Pipeline to
divert Gas either through the delivery of quantities of Gas
equal to the quantities of