RATE SCHEDULE FTS-OSF
Firm Transportation Service
Offshore Facilities
1. AVAILABILITY
1.1 This Rate Schedule is available to any party for the firm
transportation by Pipeline of Natural Gas on Pipeline's Offshore
Facilities upon the execution of an FTS-OSF Service Agreement.
Such Service Agreement shall be substantially in the form
contained in Pipeline's FERC Gas Tariff of which this Rate
Schedule FTS-OSF is a part.
1.2 Availability of service under this Rate Schedule is conditioned on
and made subject to a determination by Pipeline that capacity is
available on Pipeline's Offshore Facilities, as of the effective
date of the Service Agreement between Pipeline and Customer.
1.3 Availability of service under this Rate Schedule shall be subject
to a determination by Pipeline, based on operational
considerations, that service requested hereunder shall not cause a
reduction in Pipeline's capacity disproportionate to the service
requested.
1.4 Unless otherwise agreed to by Pipeline and subject to Section 10
of the General Terms and Conditions of this FERC Gas Tariff,
service under this Rate Schedule shall not be available to the
extent that Pipeline would be required to construct, modify,
expand or acquire any facilities to enable Pipeline to perform
the requested services; provided, however, if Customer requests
and Pipeline, on a non-discriminatory basis, elects to construct
such facilities, Customer shall, at Pipeline's request, reimburse
Pipeline for all costs and associated fees, licenses and other
expenses incurred by Pipeline for the construction, modification,
expansion or acquisition of facilities to enable Pipeline to