Enbriidge Pipelines (Midla) L. L. C.
FIFTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2009, Docket: RP09-980-000, Status: Effective
First Revised Sheet No. 38 First Revised Sheet No. 38
Superseding: Original Sheet No. 38
(c) The date on which Customer is notified that any facilities
necessary to provide the requested service are ready for
service; or
(d) The date on which any necessary governmental approvals or
authorizations are received and accepted by the appropriate
party.
3.4 Customer's Service Agreement shall be terminated if, after
commencement of initial service, Customer fails to nominate or
tender Gas within thirty (30) Days after notice by Pipeline of its
intent to terminate Customer's Service Agreement by reason of
failure of Customer to transport Gas for a six (6) Month
consecutive period.
3.5 Customer's failure to schedule transportation shall be excused by
an event of force majeure, as defined in Section 13 of the General
Terms and Conditions; provided, however, such failure to schedule
transportation shall be excused only for the duration of the force
majeure event.
4. RATE
4.1 The rate for interruptible transportation service provided under
this Rate Schedule shall be the amount negotiated by Pipeline and
Customer, which shall not be more than the maximum, nor less than
the minimum for this Rate Schedule as set forth on currently
effective Tariff Sheet No. 4A.
4.2 (a) For all services that utilize a Receipt or Delivery Point on
Pipeline's mainline system (other than services from
Receipt/Delivery Points on the T-32 lateral or other
offsystem laterals), Pipeline shall have the right to retain
one and one-half percent (1.5%) of the quantities of Gas
delivered to Pipeline for Fuel Reimbursement. Any change in
such fuel rate shall be made effective only at the beginning
of a Month.
(b) For those services involving T-32 Receipt/Delivery Points,
Pipeline shall have the right to retain, from the quantities
of Gas delivered to Pipeline, a Fuel Reimbursement
percentage applicable to service on the T-32 lateral ("T-32
Fuel Reimbursement") equal to the actual fuel and
unaccounted for on the T-32 lateral. Until changed in a
filing accepted by the FERC, the T-32 Fuel Reimbursement
percentage will be zero. Any change in such fuel rate shall
be made effective only at the beginning of a Month.
(c) For those services involving Receipt and Delivery Points
located entirely on laterals not contiguous to Pipeline's
mainline system, Pipeline shall not retain any Gas as Fuel
Reimbursement.