Enbriidge Pipelines (Midla) L. L. C.

FIFTH REVISED VOLUME NO. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/01/2009, Docket: RP09-980-000, Status: Effective

Second Revised Sheet No. 23 Second Revised Sheet No. 23

Superseding: First Revised Sheet No. 23

 

2.3 The no-notice service shall have the following characteristics:

 

(a) Pipeline shall provide firm transportation from Customer's

Point(s) of Receipt to Customer's Point(s) of delivery.

 

(b) Nominations are not required for deliveries to Point(s) of

Delivery for service under this Rate Schedule.

 

(c) No-notice service requires Customer to designate Points(s)

of Delivery with a maximum delivery MDQ (NNS MDQ). As with

the aggregate NNS MDQ, Customer's Point of Delivery NNS MDQs

shall be a uniform quantity throughout the contract year,

except that Pipeline may, on a not unduly discriminatory

basis, agree to certain differing levels in Customer's Point

of Delivery NNS MDQs over specified periods. Customer's

Point of Delivery NNS MDQs and any differing levels in such

Point of Delivery NNS MDQs, as well as the period of such

differing Point of Delivery NNS MDQ levels, shall be

specified in the executed Service Agreement. The Point of

Delivery NNS MDQs shall be a uniform quantity throughout the

Month. The sum of Customer's Point(s) of Delivery MDQs must

equal the total NNS MDQ.

 

(d) In the event a Customer subscribing to NNS fails to provide

a predetermined allocation to Pipeline pursuant to Section

16 of the General Terms and Conditions, such Customer will

be deemed to have received NNS quantities at any time that

deliveries to Customer are in excess of scheduled quantities

nominated under a Rate Schedule for firm transportation

service.

 

(e) At Customer's election, Pipeline may act as Customer's Agent

for the procurement of Gas supplies from third parties which

supplies are to be transported in accordance with this Rate

Schedule NNS.

 

(f) Unless Pipeline in its reasonable judgment otherwise

permits, Customer may not withdraw Gas from Pipeline's

system at Point(s) of Delivery at combined rates of flow

which exceed one-tenth (1/10th) of Customer's total NNS MDQ

in any one hour period.