K N Interstate Gas Transmission Co.
Second Revised Volume No. 1-B
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1994, Docket: RP94-397-000, Status: Effective
Second Revised Sheet No. 64 Second Revised Sheet No. 64 : Superseded
Superseding: Sub First Revised Sheet No. 64
GENERAL TERMS AND CONDITIONS FOR SERVICES - continued
(3) Any Gas Supply Realignment Costs actually incurred and
recovered from Shippers under Rate Schedules FT and NNS
but subsequently required by the Commission to be
refunded shall be refunded to such Shippers within sixty
(60) days after the date of the Commission order
requiring such refunds on the ratio of the Shipper's
aggregate MDQ to the total aggregate MDQ under Rate
Schedules FT and NNS for the time period during which the
Gas Supply Realignment Costs were allocated. Any Gas
Supply Realignment Costs actually incurred and deemed
recovered from Shippers under Rate Schedule IT shall be
credited to the Gas Supply Realignment Costs to be
included in the rates for Rate Schedule IT in the next
quarterly filing.
c. Within sixty (60) days from each twelve (12) month period
following the implementation date, Transporter shall file a
statement with the Commission reflecting:
(1) The aggregate amount of Gas Supply Realignment Costs
incurred and allocated to be collected during the
previous twelve (12) month period from Rate Schedule IT,
as determined pursuant to Section 26.3 d.;
(2) The aggregate amount of Gas Supply Realignment Costs
deemed collected during the previous twelve (12) month
period by Transporter under Rate Schedule IT as
determined pursuant to Section 26.3 d.
Transporter shall have the option at any time after twelve
(12) months from the initial implementation of the GSR
surcharge to file to recover any Gas Supply Realignment Costs
unrecovered through its Rate Schedule IT rates through an
alternate mechanism.