K N Interstate Gas Transmission Co.
Second Revised Volume No. 1-B
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1994, Docket: RP94-397-000, Status: Effective
First Revised Sheet No. 15 First Revised Sheet No. 15 : Superseded
Superseding: Original Sheet No. 15
GENERAL TERMS AND CONDITIONS FOR SERVICES - continued
5.2 The volume of gas delivered through each Point of Delivery and
Receipt shall be corrected to a base temperature of sixty (60)
degrees Fahrenheit by using:
a. The arithmetic average of the hourly temperatures recorded by
a properly installed continuously operated recording
thermometer, or
b. A meter containing a temperature operated device, hereinafter
referred to as a temperature compensated meter, through the
operation of which the meter correctly registers the volume,
corrected to sixty (60) degrees Fahrenheit, or
c. An assumed temperature of the gas flowing through the meters
of fifty (50) degrees Fahrenheit in the case of any small
volume delivery where Transporter does not elect to install a
recording thermometer or temperature compensated meter;
provided, however, in the event Transporter does not install a
recording thermometer or temperature compensated meter,
Shipper may install a recording thermometer and in such case
the temperature so recorded shall be used in correcting to a
temperature of sixty (60) degrees Fahrenheit.
5.3 When orifice meters are used, the specific gravity of the gas
delivered shall be determined by approved methods once a month, or
as frequently as necessary for reasonably accurate determination,
and the specific gravity so obtained shall be used in computing
volumes of gas delivered hereunder.
5.4 The components for determining the deviation from Boyle's Law, at
the pressure and temperature under which delivered, shall be
determined by tests at intervals of twelve (12) months or at such
shorter interval as is found necessary in practice and the
correction factor so determined using American Gas Association
"Report Number Eight" or American Gas Association "Project NX-19"
shall be used in the computation of deliveries until the next test.