RATE SCHEDULE IT - continued
b. FILING FEES. Any and all filings and approval fees required
in connection with Shipper's Service Agreement that
Transporter is obligated to pay to the FERC or any other
governmental authority having jurisdiction shall be reimbursed
by Shipper to Transporter. Any filing and approval fees paid
by Shippers will not be included in Transporter's cost of
service.
Any reimbursement due Transporter by Shipper pursuant to this
Section 5.3 shall be due and payable to Transporter within ten
(10) days of the date of Transporter's invoice(s) for same.
5.4 In the event of a force majeure occurrence as defined in Section 16
of the General Terms and Conditions of Transporter's FERC Gas
Tariff, Shipper shall not be relieved from its obligation to make
payment of amounts then due or which become due. If Shipper's
obligation to pay a daily imbalance charge or a portion of the
monthly balancing charge under this rate schedule is a direct
consequence of an imbalance which occurs as a result of
Transporter's force majeure as defined in Section 16 of the General
Terms and Conditions of Transporter's FERC Gas Tariff, Shipper
shall be relieved of such charges.
6. SCHEDULING OF RECEIPTS AND DELIVERIES
6.1 NOMINATIONS. If Shipper desires transportation of gas on any day
under this Rate Schedule, Shipper shall:
a. Submit a nomination through the electronic bulletin board by
10:00 a.m. CT on the day before Shipper desires
transportation. Transporter shall have no obligation to
transport gas for Shipper under this Rate Schedule if
Shipper's notice (nomination) is not timely. Nominations from
storage to on-system delivery points may be made at any time
on a prospective basis. All other nominations received after
10:00 a.m. CT will be accepted on a reasonable efforts basis,
subject to confirmation by upstream and downstream operators.