having jurisdiction; but upon request either party shall submit
to the other any such available records and charts, together with
any calculations therefrom, for inspection and verification,
subject to return within ten (10) days after receipt.
5.3 Failure of Meters
In the event a meter is out of service, or
registering inaccurately, the volume of LNG delivered hereunder
shall be estimated:
(a) By using the registration of any check meter or
meters if installed and accurately registering, or in the absence
thereof;
(b) By correcting the error, if such error is
ascertainable by calibration, test or mathematical calculation;
or
(c) In the absence of both (a) and (b) then by
estimating the quantity of delivery by mutually agreed method.
5.4 Test of Meters
The accuracy of any measuring equipment for LNG,
other than recording calorimeters, installed by either party
shall be verified at reasonable intervals by the installing party
upon notice given to the other party. Either party shall notify
the other when it desires a special test of any measuring
equipment other than recording calorimeters installed by either
party, and the parties shall thereupon cooperate to secure a
prompt verification of the accuracy of such equipment; provided
that no party shall be required to verify the accuracy of its
equipment more frequently than once in any 14-day period.
Recording calorimeters shall be verified by the installing party
not less than once per day at approximately the same hour each