Alabama-Tennessee Natural Gas Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/1993, Docket: RS92- 27-003, Status: Effective
Original Sheet No. 34 Original Sheet No. 34 : Superseded
RATE SCHEDULE FT-SG (continued)
be at a mutually agreeable interconnection between
Transporter's facilities and the facilities of the
upstream pipeline system providing service as shown in
Exhibit A to the FT-SG Contract. The total quantity
specified at the Primary Receipt Point(s) must equal the
sum of the Contract Demand and Fuel and Losses requirement
set forth in Section 8 of this Rate Schedule. Transporter
shall not be required under any circumstances to receive
gas at any Receipt Point(s) where the total quantity of gas
scheduled for receipt on any day is less than that required
for the accurate measurement of quantities to be received.
4.2 Delivery Points: The Primary Delivery Point(s) for all gas
transported by Transporter under this Rate Schedule shall
be at a mutually agreeable interconnection between
Transporter's facilities and the facilities of Shipper or
Shipper's designee as shown in Exhibit B to the FT-SG
Contract. The total quantity specified at the Primary
Delivery Point(s) must equal the Contract Demand stated in
the FT-SG Contract. Transporter shall not be required under
any circumstances to deliver gas at any Delivery Point
where the total quantity of gas scheduled for delivery in
any day is less than that required for the accurate
measurement of quantities to be delivered.
4.3 Change in Receipt and Delivery Point(s): Subject to
availability of Firm Capacity, Shipper may change the
Primary Receipt or Delivery Point(s) under its FT-SG
Contract (including redistributing the Contract Demand
amount) on a monthly basis by an amendment of Exhibits A
and/or B to the FT-SG Contract. Such amendment shall be
reflected in an executed revision of Exhibits A and/or B
submitted to Transporter by the twentieth of the month
preceding the month for which the change is desired.
Subject to available capacity, Transporter will allow a
change to designated Receipt Point(s) at any time in the
event of failure to deliver committed gas supplies because
of equipment failure, compressor malfunction, freezing, or
similar force majeure conditions. Transporter will
provide, via its Electronic Bulletin Board ("EBB") notice