Kansas Pipeline Company

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index



Effective Date: 05/11/1998, Docket: CP96-152-009, Status: Effective

Original Sheet No. 271 Original Sheet No. 271 : Superseded




attributable to firm services to

be recovered through the GSR Cost

Reservation Surcharge by the design billing

determinants underlying Kansas Pipeline's then-

effective rates applicable to Rate Schedule FT.

The Carryover GSR Cost Collection Period

shall commence on the first day of the month

following Commission approval of such filing.


17.4 Former Buyer's Obligation For Unrecovered Purchased Gas



(a) Purpose


This Section 17.4 establishes the disposition of any

unrecovered purchased gas costs incurred by Kansas

Pipeline Partnership prior to the effectiveness of

Kansas Pipeline's FERC Gas Tariff.


(b) Disposition of Unrecovered Purchased Gas Costs


Upon the effectiveness of Kansas Pipeline's FERC Gas

Tariff, and this Section 17.4, Kansas Pipeline

shall be permitted to: (1) direct bill a proportionate

share of the total unrecovered amounts remaining in

Kansas Pipeline Partnership's Unrecovered Purchased

Gas Account to each person ("Buyer") that received

service under one of Kansas Pipeline's sales rate

schedules under its Former Tariff as of the day prior

to the effective date of this Section 17.4; and

(2) direct bill a proportionate share of prior

period billing adjustments which Kansas Pipeline

shall become obligated to pay, if such prior

period adjustments arise from services provided

or Gas purchased at any time commencing November 2,

1995 through the end of the day prior to the

effectiveness of this Section.


17.4. Upon the effectiveness of this Section 17.4,

the unrecovered Account No. 191 Deferred Account

Balance shall be adjusted to include a final

reconciliation of amounts for exchange transactions