Kansas Pipeline Company

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 05/11/1998, Docket: CP96-152-009, Status: Effective

Original Sheet No. 238 Original Sheet No. 238 : Effective

 

GENERAL TERMS AND CONDITIONS (Continued)

tendered at the Point(s) of Delivery on any Day, then

Kansas Pipeline shall not be obligated to receive Gas

at the Point(s) of Receipt on such Day.

 

12.7 Should Shipper be unable to provide Quantities

of Gas scheduled at the Point(s) of Receipt on

any Day, then Kansas Pipeline shall not be obligated

to deliver Gas at the Point(s) of Delivery on such Day.

 

12.8 Kansas Pipeline shall have the unqualified right to

commingle Gas transported hereunder with Gas from other

sources, and to treat and handle all such Gas as its

own. Unless Shipper or Shipper's designee elects to

exercise its rights to process Gas for removal of

moisture, helium, natural gasoline, butane, propane, or

other liquefiables or inerts and has made arrangements

for such processing at an existing point on Kansas

Pipeline's system, Kansas Pipeline will have the

unqualified right to process such gas for the purpose

of removing such moisture, helium, natural gasoline,

butane, propane, or other liquefiables or inerts,

and the ownership of such moisture, helium,

natural gasoline, butane, propane, or other

liquefiables or inerts, shall be vested in

Kansas Pipeline. Kansas Pipeline must be advised prior

to January 1 and July 1 of each year by

Shipper or Shipper's designee for the following six (6)

months of Shipper's or Shipper's designee's exercise of

their right to process Gas for removal of such moisture,

helium, natural gasoline, butane, propane, or other

liquefiables or inerts and of the arrangements made

therefor. It is recognized that Gas delivered at a

Point of Delivery may not be the same molecules

as those received at any Point of Receipt, and

that Kansas Pipeline's sole obligation is to deliver

the Thermal Equivalent of Quantities of Gas received,

adjusted for Fuel Reimbursement.

 

12.9 Shipper shall have the responsibility to maintain a

concurrent balance between Quantities of Gas received,

adjusted for appropriate Fuel Reimbursement, and

Quantities of Gas delivered, based on the best

information available to Shipper. Kansas Pipeline shall

make available to Shipper information regarding daily