Effective Date: 05/11/1998, Docket: CP96-152-015, Status: Effective
First Revised Sheet No. 236 First Revised Sheet No. 236 : Effective
Superseding: Original Sheet No. 236
GENERAL TERMS AND CONDITIONS (Continued)
changes during the Month in the Point(s) of Delivery
designated in the Service Agreement or the Quantities
assigned thereto.
11.7(a) Subject to the availability of capacity and the
provisions of Section 7.4, Shipper may submit a
request to change a primary firm Point of Delivery
located at any point which is within the Kansas
Pipeline segment between the Point(s) of Receipt and
Point(s) of Delivery specified in the Service
Agreement or to modify the Quantity of Gas at any
primary firm Point of Delivery within the Maximum
Daily Contract Quantity specified in the Service
Agreement upon 15 Days prior written notice to Kansas
Pipeline. Such a request may be submitted once in any
Fifteen (15) Day period. A change in the primary firm
Point(s) of Delivery or modification in the Quantity
of Gas at the primary firm Point of Delivery pursuant
to this Section shall not be made so as to reduce the
reservation charges applicable under the Service
Agreement. A Shipper may add a primary Point(s) of
Delivery that is not between the Point(s) of Receipt
and Point(s) of Delivery specified in the Service
Agreement and may increase the Maximum Daily Contract
Quantity at any primary Point of Delivery over and
above the prevailing Quantities under the Service
Agreement pursuant to Section 7.
(b) A Shipper may submit a request to change any secondary