Kansas Pipeline Company
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/11/1998, Docket: CP96-152-009, Status: Effective
Original Sheet No. 234 Original Sheet No. 234 : Effective
GENERAL TERMS AND CONDITIONS (Continued)
11.5 Subject to the conditions of the Rate Schedule under
which Shipper is receiving service and the provisions of
Sections 4, 8, 9, 10 and 12 herein, Shipper may nominate
Quantities of Gas to be delivered to any Point of
Delivery identified in the Service Agreement, up to the
Quantity of Gas assigned to such Point of Delivery in
the Service Agreement.
(a) If the Shipper's Service Agreement has not been
assigned in whole or in part pursuant to Section
14 of these General Terms and Conditions, the sum
of the Quantities of Gas nominated by the Shipper
to any secondary firm Point(s) of Delivery, together
with the sum of the Quantities of Gas nominated to a
primary firm Point(s) of Delivery shall not exceed
the Maximum Daily Contract Quantity specified in
the Shipper's Service Agreement;
provided, however, if the Shipper utilizes
two (2) or more discrete pipeline segments,
the sum of the Quantities of Gas nominated by the
Shipper to all Point(s) of Delivery may exceed the
Maximum Daily Contract Quantity specified in the
Service Agreement so long as the Quantities
nominated for transportation in a pipeline segment
do not exceed the Maximum Daily Contract Quantity
applicable to such segment.
(b) If the Shipper's Service Agreement has been assigned
in part pursuant to Section 14 of these General Terms
and Conditions:
(i) the sum of the Quantities of Gas nominated by the
Replacement Shipper to any secondary firm Point(s)
of Delivery, together with the sum of the
Quantities of Gas nominated to primary firm
Point(s) of Delivery, shall not exceed the Maximum
Daily Contract Quantity in the Replacement
Shipper's Service Agreement; provided, however,if
the Replacement Shipper utilizes two (2) or more
discrete Kansas Pipeline segments, the sum of the
Quantities of Gas nominated by the Replacement
Shipper to all Point(s) of Delivery may exceed the
Maximum Daily Contract Quantity specified in the
Service Agreement so long as the Quantities