11.5 Subject to the conditions of the Rate Schedule under

which Shipper is receiving service and the provisions of

Sections 4, 8, 9, 10 and 12 herein, Shipper may nominate

Quantities of Gas to be delivered to any Point of

Delivery identified in the Service Agreement, up to the

Quantity of Gas assigned to such Point of Delivery in

the Service Agreement.

 

(a) If the Shipper's Service Agreement has not been

assigned in whole or in part pursuant to Section

14 of these General Terms and Conditions, the sum

of the Quantities of Gas nominated by the Shipper

to any secondary firm Point(s) of Delivery, together

with the sum of the Quantities of Gas nominated to a

primary firm Point(s) of Delivery shall not exceed

the Maximum Daily Contract Quantity specified in

the Shipper's Service Agreement;

provided, however, if the Shipper utilizes

two (2) or more discrete pipeline segments,

the sum of the Quantities of Gas nominated by the

Shipper to all Point(s) of Delivery may exceed the

Maximum Daily Contract Quantity specified in the

Service Agreement so long as the Quantities

nominated for transportation in a pipeline segment

do not exceed the Maximum Daily Contract Quantity

applicable to such segment.

 

(b) If the Shipper's Service Agreement has been assigned

in part pursuant to Section 14 of these General Terms

and Conditions:

 

(i) the sum of the Quantities of Gas nominated by the

Replacement Shipper to any secondary firm Point(s)

of Delivery, together with the sum of the

Quantities of Gas nominated to primary firm

Point(s) of Delivery, shall not exceed the Maximum

Daily Contract Quantity in the Replacement

Shipper's Service Agreement; provided, however,if

the Replacement Shipper utilizes two (2) or more

discrete Kansas Pipeline segments, the sum of the

Quantities of Gas nominated by the Replacement

Shipper to all Point(s) of Delivery may exceed the

Maximum Daily Contract Quantity specified in the

Service Agreement so long as the Quantities