Kansas Pipeline Company

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 05/11/1998, Docket: CP96-152-009, Status: Effective

Original Sheet No. 209 Original Sheet No. 209 : Effective

 

GENERAL TERMS AND CONDITIONS (Continued)

oral or telephonic notice to Shipper, to refuse

to accept all or any portion of such quality deficient

Gas. If Kansas Pipeline refuses to accept Gas

tendered by Shipper because such

Gas does not conform to the specifications

set forth herein, Shipper shall not be relieved

of its obligation to pay any Access, Reservation,

Transmission or any other applicable charge in

Kansas Pipeline's tariff, Rate Schedules or

Service Agreements.

 

3.3 Kansas Pipeline shall have the unqualified

right to commingle Gas transported hereunder

with Gas from other sources. It is recognized

that Gas delivered at a Point of Delivery may

not be the same molecules as those received

at a Point of Receipt. The Quantities of Gas

delivered pursuant to a Transportation Agreement

at a Point of Delivery shall be thermally

equivalent to the Quantities of Gas received

at the Point of Receipt, adjusted for Fuel

Reimbursement.

 

4. MEASUREMENT

 

4.1 Quantities of Gas received or delivered hereunder

at each Point of Receipt and Point of Delivery shall

be determined by either Kansas Pipeline or Shipper

responsible for measurement at such point, as listed

on Exhibit A of the Service Agreement.

 

The heating value, specific gravity and super-

compressibility (Mol percent of nitrogen and carbon

dioxide) values of the Gas shall be determined at the

beginning of receipt and monthly thereafter, or at

such frequency consistent with generally accepted

practices in the natural gas industry.

Shipper may be required to test, at the receipt

meter, for bacteria or bacterial agents if

Kansas Pipeline so requires. Tests for bacteria

or bacterial agents shall be conducted on samples taken

from the meter run or other appurtenant piping using

American Petroleum Institute (API) test method API-RP38

or any other test method acceptable to Kansas Pipeline