Kansas Pipeline Company
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1999, Docket: TM00-1-166-000, Status: Effective
Fourth Substitute Original Sheet No. 31C Fourth Substitute Original Sheet No. 31C : Effective
Superseding: Third Substitute Original Sheet No. 31C
NON-CONFORMING SERVICE AGREEMENT
RATE SUMMARY SHEET
Atmos Energy Corporation - UCG at Heritage Park
The Contract Demand Quantity (CDQ) for transportation under
this Agreement is 4,000 Dt/d. The price to be paid for this
CDQ, pursuant to Agreement between Kansas Pipeline Company
(KPC) and United Cities Gas Company (at Heritage Park), a
division of Atmos Energy Corporation, shall be:
April 1, 1999 through March 31, 2000
- $0.3140 per Dt
Fuel
Reimbursement *
Nov-Mar Apr-Oct
Zone 1 1.5751% 1.2500%
Zone 2 0.0000% 0.0000%
Zone 3 0.0000% 0.0000%
*Compressor fuel, lost and unaccounted for gas
Rates are additive. A Shipper transporting gas through more than one
Zone shall pay the applicable rates for each Zone.