6. POINTS OF RECEIPT AND DELIVERY
6.1 Point(s) of Receipt. The Point(s) of Receipt under this
ITS Rate Schedule shall be at such points as may be agreed
to by the parties as set forth in executed ITS Agreements
between Transporter and Shipper and authorized by FERC
where Shipper shall deliver, or cause to be delivered,
natural gas to Transporter for transportation service.
Shipper may designate Transporter's Master Receipt Point
List, which shall include all of Transporter's authorized
Points of Receipt. The Master Receipt Point List is
included in Section 18 of the General Terms and Conditions
which is part of this Rate Schedule ITS; provided, however,
that Transporter may update such Master Receipt Point List
from time to time as new receipt points are added to Trans-
porter's system.
6.2 Point(s) of Delivery. The Point(s) of Delivery under this
ITS Rate Schedule shall be the points where Transporter shall
deliver natural gas to or for the account for Shipper after
transportation and shall be at such points as may be agreed
to by the parties as set forth in executed ITS Agreements
between Transporter and Shipper and authorized by FERC.
Shipper may designate Transporter's Master Delivery Point
List, which shall include all of Transporter's authorized
Points of Delivery. The Master Delivery Point List is attached
to this ITS Rate Schedule as Exhibit B; provided, however,
that Transporter may update such Master Delivery Point List
from time to time as new delivery points are added to
Transporter's system.