Ozark Gas Transmission System
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/03/1991, Docket: RP91-208-000, Status: Effective
Original Sheet No. 110 Original Sheet No. 110 : Superseded
ARTICLE VI
RATE SCHEDULE AND CHARGES
6.1 Shipper shall pay Transporter for the service
hereunder an amount determined in accordance with
Transporter's FTS Rate, the applicable provisions
of Transporter's FTS Rate Schedule, and the
General Terms and Conditions of Transporter's FERC
Gas Tariff, all as may be revised from time to
time. Such FTS Rate Schedule and General Terms
and Conditions are incorporated by reference and
made a part hereof.
6.2 Transporter may seek authorization from the FERC
and/or other appropriate body to change any
rate(s) and/or term(s) set forth herein or in the
FTS Rate Schedule. Nothing herein shall be
construed to deny Shipper any rights it may have
under the Natural Gas Act or the Natural Gas
Policy Act including the right to participate
fully in rate proceedings by intervention or
otherwise to contest increased rates in whole or
in part.
ARTICLE VII
REDUCTION IN CAPACITY
7.1 If Transporter's capacity is reduced for any
reason and a reduction of the quantity of gas
being transported hereunder is required, Shipper's
MDQ shall be reduced pro rata with the MDQ's of
the other firm Shippers during the period of such
capacity reduction.