RATE SCHEDULE FTS
FIRM TRANSPORTATION SERVICE
(Continued)
7. POINTS OF RECEIPT AND DELIVERY
7.1 Point(s) of Receipt. The Point(s) of Receipt under this
FTS Rate Schedule shall be at such points as may be agreed
to by the parties as set forth in executed FTS Agreements
between Transporter and Shipper and authorized by FERC
where Shipper shall deliver, or cause to be delivered,
natural gas to Transporter for transportation service.
Shipper may designate Transporter's Master Receipt Point
List ("MRPL"), which shall include all of Transporter's
authorized Points of Receipt. The MRPL is included in
Section 18 of the General Terms and Conditions which is part
of this Rate Schedule FTS; provided, however, that
Transporter may update such MRPL from time to time as
new receipt points are added to Transporter's system.
Shipper shall have the right to adjust capacity at existing
Point(s) of Receipt or deliver gas into Point(s) of Receipt
not originally set forth in the executed FTS Agreements;
provided, however, that in order to provide service at such
adjusted or additional Point(s) of Receipt, Transporter
shall not be required to interrupt or curtail firm
transportation services already being provided by
Transporter to other Shippers at such adjusted or additional
Point(s) of Receipt. Any new Point(s) of Receipt agreed to
by the parties pursuant to this Section shall be added to
the executed FTS Agreements.
7.2 Point(s) of Delivery. The Point(s) of Delivery under this
FTS Rate Schedule shall be the points where Transporter
shall deliver natural gas to or for the account for Shipper
after transportation and shall be at such points as may be
agreed to by the parties as set forth in executed FTS
Agreements between Transporter and Shipper and authorized
by FERC.