Ozark Gas Transmission System

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 09/03/1991, Docket: RP91-208-000, Status: Effective

Original Sheet No. 84 Original Sheet No. 84 : Superseded

 

 

RATE SCHEDULE FTS

FIRM TRANSPORTATION SERVICE

 

 

1. AVAILABILITY

 

This FTS Rate Schedule is available for firm

transportation service by Ozark Gas Transmission

System (hereinafter called Transporter) for any person

(hereinafter called Shipper) provided that (i)

Transporter and Shipper have entered into appropriate

Firm Transportation Service Agreement(s) (FTS Agree-

ment(s)) applicable to the requested Point(s) of

Delivery for a term to be set forth in the FTS

Agreement(s) in the form contained in Transporter's

FERC Gas Tariff, and (ii) Shipper meets the

creditworthiness criteria set forth in Section 5 of

this FTS Rate Schedule.

 

 

2. APPLICABILITY AND CHARACTER OF SERVICE

 

2.1 Transporter shall accept, for the account of

Shipper at the Point(s) of Receipt on any day the

quantity of natural gas tendered by or for the

account of Shipper; provided, however,

Transporter shall not be obligated to receive at

any Point(s) of Receipt on any day a quantity of

natural gas in excess of the applicable Maximum

Daily Quantity (MDQ) plus Fuel Usage and

Applicable Shrinkage, nor shall Transporter be

obligated to receive at all Point(s) of Receipt a

cumulative quantity of natural gas in excess of

the MDQ plus Fuel Usage and Applicable Shrinkage

without the consent of Transporter. Upon receipt

of such natural gas for Shipper's account,

Transporter shall transport and deliver for the

account of Shipper an Equivalent Quantity of

natural gas at the Point(s) of Delivery;

provided, however, Transporter shall not be

obligated to deliver at any Point(s) of Delivery

on any day a quantity of natural gas in excess of

the applicable MDQ, nor shall Transporter be

obligated to deliver at all Point(s) of Delivery