Trunkline LNG Company
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/29/1994, Docket: CP87-418-004, Status: Effective
First Revised Sheet No. 55 First Revised Sheet No. 55 : Effective
Superseding: Original Sheet No. 55
RATE SCHEDULE PLNG-2 (Continued)
provided in section 3.2 or section 9.4, shall continue in
effect through the 180th day following the earlier of the end
of the Contract Year in which an aggregate quantity of LNG
of not less than 3,300,000,000 MMBtu shall have been sold and
purchased under Purchase Agreements or the expiration of 20
Contract Years following the Effective Date.
ARTICLE III
Terminal Services
3.1 Subject to the provisions of section 3.2 and the terms
of this Agreement, TLC shall provide LNG terminal services to
Pan National consisting of the receipt, storage, and
regasification of LNG and the redelivery of regasified LNG.
TLC shall make available to and operate for the benefit of Pan
National sufficient operating capacity of TLC's terminal
facilities to accommodate the quantities of LNG purchased by
Pan National under the Purchase Agreements.
3.2 In the event that the Contract of Sale and Purchase of
Liquefied Natural Gas (the LNG Contract"), dated September 17,
1975, between SONATRACH and Panhandle Eastern Pipe Line
Company, shall cease to be suspended and the performance
thereof shall have been agreed to be resumed, all in accordance
with section 10 of the Settlement Agreement, dated July 21,
1986, among SONATRACH, Panhandle and TLC, then TLC shall give
to Pan National notice of the expected date on which
-5-